Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality
Add to watchlistA centre for entrepreneurs with co-working spaces on land allocated by the municipality, which brings in the utilities and access roads.
Budget (BAC)
Actual cost
34% of budget
Progress
Estimate at completion
SAR +496K
SPI · CPI
Forecast finish
28 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure29 June 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-12-15 | 2026-02-14 | +61 days | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-04-19 | 2026-08-04 | +107 days | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-10-23 | 2027-03-01 | +129 days | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.sa | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2027-04-28 | 2027-07-05 | +68 days | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-08-31 | 2027-09-27 | +27 days | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
33%Awaiting acceptance
12%Not handed in
55%Deliverable flow
Display options
| Project plan & baseline034-D1 | 3% | CRT-034-01 | Approved | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2025-10-14 | V1 | 3 of 3 |
| Monitoring & reporting034-D2 | 3% | CRT-034-02 | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2025-12-15 | V1 | 3 of 3 |
| Detailed design034-D3 | 7% | CRT-034-03 | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-02-16 | V1 | 3 of 3 |
| Permits & approvals034-D4 | 6% | CRT-034-04 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreP-010t.alanazi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-04-19 | V1 | 3 of 3 |
| Site works & excavation034-D5 | 14% | CRT-034-05 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreP-010t.alanazi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-06-20 | V1 | 3 of 3 |
| Structure034-D6 | 12% | — | Submitted | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-08-22 | V1 | 1 of 3 |
| Finishes034-D7 | 12% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-10-23 | V0 | 0 of 3 |
| Supply034-D8 | 10% | — | Draft | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-12-24 | V0 | 0 of 3 |
| Installation034-D9 | 10% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2027-02-25 | V0 | 0 of 3 |
| Testing & commissioning034-D10 | 9% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreP-010t.alanazi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2027-04-28 | V0 | 0 of 3 |
| Provisional acceptance034-D11 | 7% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2027-06-30 | V0 | 0 of 3 |
| Final acceptance034-D12 | 7% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreP-010t.alanazi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2027-08-31 | V0 | 0 of 3 |
| Total · 12 | 100% |