PRJ-2026-034At risk4ExecutionConstructionIn progress

Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality

Add to watchlist

A centre for entrepreneurs with co-working spaces on land allocated by the municipality, which brings in the utilities and access roads.

Early warning: ⁦55%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 11.9M

Actual cost

SAR 4.1M

⁦34%⁩ of budget

Progress

⁦33%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 12.4M

SAR +496K

SPI · CPI

0.89Schedule performance index · 0.890.96Cost performance index · 0.96

Forecast finish

⁦2027-09-28⁩

28 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure29 June 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

2Achieved
0On track
2At risk
1Late
Average delay78 days
Jan 26Apr 26Jul 26Oct 26Jan 27Apr 27Jul 27Oct 27
Contractual
Build completePlanned: ⁦2026-10-23⁩Forecast / actual: ⁦2027-03-01⁩Delay: 129 daysG3 +129
Executive
Project plan approvedPlanned: ⁦2025-12-15⁩Forecast / actual: ⁦2026-02-14⁩Delay: 61 daysG1 +61
Payment
Final handoverPlanned: ⁦2027-08-31⁩Forecast / actual: ⁦2027-09-27⁩Delay: 27 daysG5 +27
Regulatory
Testing & acceptance completePlanned: ⁦2027-04-28⁩Forecast / actual: ⁦2027-07-05⁩Delay: 68 daysG4 +68
Project
Designs approvedPlanned: ⁦2026-04-19⁩Forecast / actual: ⁦2026-08-04⁩Delay: 107 daysG2 +107

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-12-15⁩⁦2026-02-14⁩⁦+61⁩ daysEng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.saAchieved1Approved
Designs approvedMS-G2Project⁦2026-04-19⁩⁦2026-08-04⁩⁦+107⁩ daysEng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-10-23⁩⁦2027-03-01⁩⁦+129⁩ daysEng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.saLate0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2027-04-28⁩⁦2027-07-05⁩⁦+68⁩ daysEng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.saAt risk0Not requested
Final handoverMS-G5Payment⁦2027-08-31⁩⁦2027-09-27⁩⁦+27⁩ daysEng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.saAt risk0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦33%⁩

Awaiting acceptance

⁦12%⁩

Not handed in

⁦55%⁩

Deliverable flow

Pick a stage to filter the register
⁦12⁩ results
Export CSV
Project plan & baseline034-D1⁦3%⁩CRT-034-01ApprovedEng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.saEng. Abdulrahman S. Al-Harbi⁦2025-10-14⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting034-D2⁦3%⁩CRT-034-02ApprovedEng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.saEng. Abdulrahman S. Al-Harbi⁦2025-12-15⁩V1⁦3⁩ of ⁦3⁩
Detailed design034-D3⁦7%⁩CRT-034-03ApprovedEng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.saEng. Abdulrahman S. Al-Harbi⁦2026-02-16⁩V1⁦3⁩ of ⁦3⁩
Permits & approvals034-D4⁦6%⁩CRT-034-04ApprovedEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreP-010t.alanazi@chamber.saEng. Abdulrahman S. Al-Harbi⁦2026-04-19⁩V1⁦3⁩ of ⁦3⁩
Site works & excavation034-D5⁦14%⁩CRT-034-05ApprovedEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreP-010t.alanazi@chamber.saEng. Abdulrahman S. Al-Harbi⁦2026-06-20⁩V1⁦3⁩ of ⁦3⁩
Structure034-D6⁦12%⁩—SubmittedEng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.saEng. Abdulrahman S. Al-Harbi⁦2026-08-22⁩V1⁦1⁩ of ⁦3⁩
Finishes034-D7⁦12%⁩—DraftEng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.saEng. Abdulrahman S. Al-Harbi⁦2026-10-23⁩V0⁦0⁩ of ⁦3⁩
Supply034-D8⁦10%⁩—DraftEng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.saEng. Abdulrahman S. Al-Harbi⁦2026-12-24⁩V0⁦0⁩ of ⁦3⁩
Installation034-D9⁦10%⁩—DraftEng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.saEng. Abdulrahman S. Al-Harbi⁦2027-02-25⁩V0⁦0⁩ of ⁦3⁩
Testing & commissioning034-D10⁦9%⁩—DraftEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreP-010t.alanazi@chamber.saEng. Abdulrahman S. Al-Harbi⁦2027-04-28⁩V0⁦0⁩ of ⁦3⁩
Provisional acceptance034-D11⁦7%⁩—DraftEng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.saEng. Abdulrahman S. Al-Harbi⁦2027-06-30⁩V0⁦0⁩ of ⁦3⁩
Final acceptance034-D12⁦7%⁩—DraftEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreP-010t.alanazi@chamber.saEng. Abdulrahman S. Al-Harbi⁦2027-08-31⁩V0⁦0⁩ of ⁦3⁩
Total · 12⁦100%⁩
⁦1⁩–⁦12⁩ of ⁦12⁩