Early warning: 55% chance of slipping within 60 days
Budget (BAC)
SAR 11.9M
Actual cost
SAR 4.1M
34% of budget
Progress
33%Awaiting acceptance 12%
Estimate at completion
SAR 12.4M
SAR +496K
SPI · CPI
0.89Schedule performance index · 0.890.96Cost performance index · 0.96
Forecast finish
2027-09-28
28 days behind baseline
Execution·Stage 4 of 5
Next gate:Closure29 June 2027
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+27 days vs approved
Baseline (original = approved)2027-08-31
Current forecast2027-09-27
By earned schedule2028-12-15
Critical activities
8
of 10 open activities
Late activities
7
past their baseline finish
Schedule performance
0.49
earned ÷ planned value
Next milestone
in 124 days
Build complete
Layers
Compare with
Expand allCollapse all
ActivityOwnerForecast finishProgress
2025
2026
2027
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Today
2027-09-2733%
Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region MunicipalityPlanned: 2025-07-06 → 2027-08-31Forecast: 2025-07-06 → 2027-09-27Float: 0d