PRJ-2026-034At risk4ExecutionConstructionIn progress

Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality

Add to watchlist

A centre for entrepreneurs with co-working spaces on land allocated by the municipality, which brings in the utilities and access roads.

Early warning: ⁦55%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 11.9M

Actual cost

SAR 4.1M

⁦34%⁩ of budget

Progress

⁦33%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 12.4M

SAR +496K

SPI · CPI

0.89Schedule performance index · 0.890.96Cost performance index · 0.96

Forecast finish

⁦2027-09-28⁩

28 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure29 June 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started

Periodic update cards

Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.

Period

October 2026

Draft
Progress
⁦33%⁩
Planned
⁦37%⁩
SPI
0.89
Open the card

Periodic update cards

PeriodStatusProgressCurrent stepDate
October 2026UPD-034-2026-10Draft⁦33%⁩—⁦2026-10-26⁩
September 2026UPD-034-2026-09Approved⁦31%⁩—⁦2026-10-02⁩
August 2026UPD-034-2026-08Approved⁦29%⁩—⁦2026-09-02⁩