Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-034At risk4ExecutionConstructionIn progress

Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality

Add to watchlist

A centre for entrepreneurs with co-working spaces on land allocated by the municipality, which brings in the utilities and access roads.

Early warning: ⁦55%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 11.9M

Actual cost

SAR 4.1M

⁦34%⁩ of budget

Progress

⁦33%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 12.4M

SAR +496K

SPI · CPI

0.89Schedule performance index · 0.890.96Cost performance index · 0.96

Forecast finish

⁦2027-09-28⁩

28 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure29 June 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Riyadh Chamber of Commerce & Industry

Project charter

Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality

APPROVEDV2Approved ⁦2025-07-04⁩

1Project identity

Required at this stage
Project name
Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality
Project code
PRJ-2026-034
Project sponsor
Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreP-010t.alanazi@chamber.sa
Project manager
Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.sa
Project owner
Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa
Portfolio & programme
New Headquarters & Investment Assets PortfolioNew Headquarters & Investment Assets Programme
Type & methodology
Infrastructure · Construction
Current phase
4Execution

2Background & rationale

Required at this stage

A centre for entrepreneurs with co-working spaces on land allocated by the municipality, which brings in the utilities and access roads.

3Objectives

Required at this stage
  1. 1Empower entrepreneurship, SMEs and employment
  2. 2The chamber’s services across Riyadh city and its governorates

4Scope

Required at this stage

In scope

  • A centre for entrepreneurs with co-working spaces on land allocated by the municipality, which brings in the utilities and access roads.
  • Saudi Building Code compliance
  • An approved plan to keep member services and training running during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Saudi Building Code compliance
  2. 2An approved plan to keep member services and training running during the works
  3. 3Civil-defence requirements

6Deliverables

Required at this stage
1Project management plan⁦2025-08-06⁩
2Main deliverable — stage 1⁦2026-08-11⁩
3Main deliverable — final stage⁦2027-05-13⁩
4Final report⁦2027-08-31⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2025-07-04⁩
  2. Contract signed⁦2025-11-09⁩
  3. 50% of works complete⁦2026-08-11⁩
  4. Provisional acceptance⁦2027-06-29⁩
  5. Closure⁦2027-08-31⁩

8Budget

Required at this stage
  • Main contract⁦72.0%⁩8.6M
  • Supervision & consulting⁦14.0%⁩1.7M
  • Internal team⁦9.0%⁩1.1M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩595K
The owning sector’s approved budgetTotal11.9M

9Timeline

Required at this stage
Start
2025-07-0611 Muharram 1447 AH
Baseline finish
2027-08-3129 Rabiʻ I 1449 AH
Duration
⁦26⁩ months

10Key risks

Required at this stage
  • HighMunicipality late bringing utilities and access roads to the site

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the chamber
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close