PRJ-2026-034At risk4ExecutionConstructionIn progress

Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality

Add to watchlist

A centre for entrepreneurs with co-working spaces on land allocated by the municipality, which brings in the utilities and access roads.

Early warning: ⁦55%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 11.9M

Actual cost

SAR 4.1M

⁦34%⁩ of budget

Progress

⁦33%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 12.4M

SAR +496K

SPI · CPI

0.89Schedule performance index · 0.890.96Cost performance index · 0.96

Forecast finish

⁦2027-09-28⁩

28 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure29 June 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 11.9M split into spent, committed and left, with the estimate at completion

Forecast overrun SAR 496K
EAC SAR 12.4M
Revised request SAR 11.9M
  • Actual spendSAR 4.1M
  • Committed, not spentSAR 6.2M
  • Allotted, uncommittedSAR 1.3M
  • Contingency availableSAR 357K

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 10.2M
Original budgetwhen the first baseline was approved
SAR 11.9M
Approved budgetafter approved change requests
SAR 11.9M
Current budgetavailable to spend now
SAR 11.9M
Revised budgetif the pending changes are approved
SAR 11.9M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 10.3M
Contracts1 active contract
SAR 9.8M
Purchase orders⁦3⁩ orders
SAR 450K
Remaining budgetapproved less actual
SAR 7.8M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 4.1M
Accrualswork done, not yet invoiced
SAR 164K
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 12.4M
ContingencySAR 238K drawn of SAR 595K
SAR 357K

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 10.2M
ApprovedSAR 11.9M
Estimate at completionSAR 12.4M
Approved is SAR 1.7M (⁦16.3%⁩) above the estimate
The estimate at completion is SAR 2.2M (⁦21.1%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2025-04-22⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-51034
  • WBS elements⁦5⁩ elements · P-2026-034.01 …
  • Purchase orders⁦3⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦6⁩ posted · ⁦1⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 238K drawn of SAR 595K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 238K

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance0.690.750.750.75⁦−0.05⁩
2Design & permits1.391.491.491.49⁦−0.10⁩
3Civil works4.393.901.864.56⁦−0.17⁩
4MEP works3.462.800.003.70⁦−0.24⁩
5Handover1.621.310.001.73⁦−0.11⁩
Unallocated contingency0.360.000.000.18⁦+0.18⁩
Total11.9010.254.0912.40⁦−0.50⁩

Budget split

WBS

SAR 11.9M

Budget

  • Management & governanceSAR 692.6K⁦6%⁩
  • Design & permitsSAR 1.4M⁦12%⁩
  • Civil worksSAR 4.4M⁦37%⁩
  • MEP worksSAR 3.5M⁦29%⁩
  • HandoverSAR 1.6M⁦14%⁩
  • Unallocated contingencySAR 357K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2028-12-15⁩+472

SPI(t) ⁦0.63⁩ against the approved finish ⁦2027-08-31⁩

Planned valuePV
SAR 8M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 3.9M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 4.1M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 11.9M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦−0.16⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−4.05⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
0.96
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.49
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 12.4M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 8.3M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦−0.50⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.02
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 12.4M
  • If the rest goes to planSAR 12.1M
  • At cost and schedule performanceSAR 21M
  • The PM’s bottom-up estimateSAR 12.4M
  • To stay within SAR 11.9M, cost performance on the rest must rise to ⁦1.02⁩ — above what has been achieved.

Estimate at completion at that performance

SAR 12.4M

Variance at completion: ⁦−0.50⁩ SAR M