Original
Original baseline
- Finish
- 2027-08-31
- Budget
- SAR 11.9M
- 17 activities
Approved with the project plan at the planning gate.
Approved 2025-07-06 · by Eng. Turki A. Al-Anazi
A centre for entrepreneurs with co-working spaces on land allocated by the municipality, which brings in the utilities and access roads.
Budget (BAC)
Actual cost
34% of budget
Progress
Estimate at completion
SAR +496K
SPI · CPI
Forecast finish
28 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure29 June 2027
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-07-06 · by Eng. Turki A. Al-Anazi
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Ibrahim A. Al-Ghamdi
What changed from version A to version B
Finish
2027-08-312027-09-27
+27 days
Budget
SAR 11.9MSAR 11.9M
0.00 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference