Execution
Periodic update card
Progress, status, risks and support requested
- Form no.
- RC-PMO-F07
- Template edition
- 2.2
- Version
- V1
- Form date
- 2026-09-02
- Hijri
- 20 Rabiʻ I 1448 AH
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-034
- Project
- Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality
- Portfolio
- New Headquarters & Investment Assets Portfolio
- Sector
- Training & Employment Centre
- Sponsor
- Eng. Turki A. Al-Anazi
- Project manager
- Eng. Ibrahim A. Al-Ghamdi
1ProgressAuto-filled
From the live data: accepted deliverables, the schedule and finance on the period’s last day.
Actual progress
29%
Planned to date
32%
SPI
0.91
Actual cost
SAR 3.6M
Main achievements this periodFilled by the project manager
Work went to the approved plan for the period, with the due deliverables handed in.
2Status
- Overall healthAuto-filled
- At risk
- StageAuto-filled
- Execution
- Forecast finishAuto-filled
- 2027-09-28
The PM’s comment on the statusFilled by the project manager
The variance from the baseline stands because of late integrations; the corrective plan is running and followed weekly.
3Risks and impedimentsAuto-filled
4Support requested
What the project needs from leadership or the committeesFilled by the project manager
Approve change request CR-2026-012 for three integration engineers (SAR 49K), and the Secretary-General to press the NIC on the Nafath environment.
- Includes financial supportAuto-filled
- Yes
Approval logChain: Periodic update approval · version 1
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction Projects | Submitted | — | 2026-09-02 11:56 |
| 2 | PMO check | Methodology review | Ghada A. Al-ShahraniPMO — analyst | Approved | The reading agrees with the schedule and finance. | 2026-09-03 09:00 |
| 3 | Sponsor review & approval | Technical acceptance | Eng. Turki A. Al-AnaziProject sponsor | Approved | — | 2026-09-07 10:07 |
Signatures
PMO check
Ghada A. Al-Shahrani
Approved2026-09-03
Sponsor review & approval
Eng. Turki A. Al-Anazi
Approved2026-09-07