Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-034At risk4ExecutionConstructionIn progress

Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality

Add to watchlist

A centre for entrepreneurs with co-working spaces on land allocated by the municipality, which brings in the utilities and access roads.

Early warning: ⁦55%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 11.9M

Actual cost

SAR 4.1M

⁦34%⁩ of budget

Progress

⁦33%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 12.4M

SAR +496K

SPI · CPI

0.89Schedule performance index · 0.890.96Cost performance index · 0.96

Forecast finish

⁦2027-09-28⁩

28 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure29 June 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality

PRJ-2026-034 · Training & Employment Centre · External · WP-2025-034

In progressAt risk4ExecutionProject manager: Eng. Ibrahim A. Al-Ghamdi · Sponsor: Eng. Turki A. Al-Anazi
Progress
⁦33%⁩ / ⁦37%⁩
SPI · CPI
0.89 · 0.96
Spend
SAR 4.1M / SAR 11.9M
Estimate at completion
SAR 12.4M

Schedule

⁦4%⁩ behind⁦33%⁩

Planned to date ⁦37%⁩

Forecast finish: 2027-09-2827 Rabiʻ II 1449 AH · 28 days late

SPI0.89Schedule performance index · 0.89CPI0.96Cost performance index · 0.96

Health dimensions

At risk

Last update: 2026-09-0220 Rabiʻ I 1448 AH · Update overdue

Deliverables

⁦4⁩ of ⁦7⁩ due deliverables accepted on time (⁦57%⁩)

Next milestones

  • Build complete2027-03-0122 Ramadan 1448 AH
  • Testing & acceptance complete2027-07-051 Safar 1449 AH
  • Final handover2027-09-2726 Rabiʻ II 1449 AH

Top risks

  • Municipality late bringing utilities and access roads to the site16

Open impediments

  • Monthly progress reports incomplete · Overdue

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SAR 11.9M: 0 on track and 0 red or critical. Weighted progress is 33% against 37% planned, spend SAR 4.1M, and EAC SAR 12.4M (SAR 0.5M over).

No project is more than a month behind baseline.

Riyadh Chamber of Commerce & Industry · prepared by Eng. Ibrahim A. Al-Ghamdi in MunjazInternal

Status: At risk ·Project page

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close