Riyadh ChamberMunjaz11My actionsNotifications

Certificate ⁦7⁩ — September 2026

Entrepreneurship centre & co-working spaces — construction

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
7
Date
⁦2026-10-15⁩
Hijri
4 Jumada I 1448 AH
Reference
PAY-2026-022

Interim payment certificate no. (⁦7⁩)

For the work of September 2026

Contract number
RC/2025/025
Supplier-portal reference
2504860719
Contract
Entrepreneurship centre & co-working spaces — construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality
Contract period
⁦2025-08-03⁩ — ⁦2027-08-31⁩
Original contract value
9,800,000
Current contract value
9,800,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date3,500,000
2Less: previous certificates(3,135,000)
3Value of work in this certificate365,000
4Less: retention (⁦10%⁩)(36,500)
5Less: advance payment recovery (⁦10%⁩)(36,500)
6Less: delay and breach penalties0
7Total deductions(73,000)
8Net before VAT292,000
9Add: value added tax (15%)43,800
10Net amount payable to the contractor335,800

Amount in words: Three hundred thirty-five thousand eight hundred Saudi riyals only

Retention held up to this certificate: SAR 350K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation686,000512,95052,300565,250⁦82%⁩
Earthworks & foundations1,764,000797,70084,300882,000⁦50%⁩
Concrete & structural works3,038,0001,068,300125,2001,193,500⁦39%⁩
Mechanical, electrical & plumbing2,352,000519,00069,000588,000⁦25%⁩
Finishes & external works1,470,000206,70029,550236,250⁦16%⁩
Testing & commissioning490,00030,3504,65035,000⁦7%⁩
Total9,800,0003,135,000365,0003,500,000⁦36%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2026-10-15⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Awaiting signature

Project manager

Eng. Ibrahim A. Al-Ghamdi

Later

Finance & contracts

Khalid N. Al-Mutairi

Later

Final approver

Dr. Abdullah S. Al-Qahtani

Later
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Current step: Engineer verifies quantities

  1. Certificate submitted⁦2026-10-15⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities8 days overdue2026-10-209 Jumada I 1448 AH

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Waiting for Eng. Ibrahim A. Al-Ghamdi
  3. Project manager certifies

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

  4. Payment order prepared

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

  5. Final approval

    Dr. Abdullah S. Al-Qahtani · Secretary-General

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-09-24⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ibrahim A. Al-Ghamdi → Dr. Abdullah S. Al-Qahtani

Certificate history

15 October 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-10-15 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close