Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 6
- Date
- 2026-09-13
- Hijri
- 2 Rabiʻ II 1448 AH
- Reference
- PAY-2025-025-06
Interim payment certificate no. (6)
For the work of August 2026
- Contract number
- RC/2025/025
- Supplier-portal reference
- 2504860719
- Contract
- Entrepreneurship centre & co-working spaces — construction
- Contractor
- Al-Bunyan Al-Rasekh Contracting Co.
- Contractor VAT number
- 310102487310003
- Project
- Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality
- Contract period
- 2025-08-03 — 2027-08-31
- Original contract value
- 9,800,000
- Current contract value
- 9,800,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 3,135,000 |
| 2 | Less: previous certificates | (2,833,500) |
| 3 | Value of work in this certificate | 301,500 |
| 4 | Less: retention (10%) | (30,150) |
| 5 | Less: advance payment recovery (10%) | (30,150) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (60,300) |
| 8 | Net before VAT | 241,200 |
| 9 | Add: value added tax (15%) | 36,180 |
| 10 | Net amount payable to the contractor | 277,380 |
Amount in words: Two hundred seventy-seven thousand three hundred eighty Saudi riyals only
Retention held up to this certificate: SAR 313.5K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 686,000 | 462,350 | 43,950 | 506,300 | 74% |
| Earthworks & foundations | 1,764,000 | 719,500 | 70,500 | 790,000 | 45% |
| Concrete & structural works | 3,038,000 | 965,700 | 103,350 | 1,069,050 | 35% |
| Mechanical, electrical & plumbing | 2,352,000 | 470,550 | 56,150 | 526,700 | 22% |
| Finishes & external works | 1,470,000 | 187,750 | 23,850 | 211,600 | 14% |
| Testing & commissioning | 490,000 | 27,650 | 3,700 | 31,350 | 6% |
| Total | 9,800,000 | 2,833,500 | 301,500 | 3,135,000 | 32% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Hamad S. Al-Hajri
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Ibrahim A. Al-Ghamdi
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani