Certificate ⁦6⁩ — August 2026

Entrepreneurship centre & co-working spaces — construction

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
6
Date
⁦2026-09-13⁩
Hijri
2 Rabiʻ II 1448 AH
Reference
PAY-2025-025-06

Interim payment certificate no. (⁦6⁩)

For the work of August 2026

Contract number
RC/2025/025
Supplier-portal reference
2504860719
Contract
Entrepreneurship centre & co-working spaces — construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality
Contract period
⁦2025-08-03⁩ — ⁦2027-08-31⁩
Original contract value
9,800,000
Current contract value
9,800,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date3,135,000
2Less: previous certificates(2,833,500)
3Value of work in this certificate301,500
4Less: retention (⁦10%⁩)(30,150)
5Less: advance payment recovery (⁦10%⁩)(30,150)
6Less: delay and breach penalties0
7Total deductions(60,300)
8Net before VAT241,200
9Add: value added tax (15%)36,180
10Net amount payable to the contractor277,380

Amount in words: Two hundred seventy-seven thousand three hundred eighty Saudi riyals only

Retention held up to this certificate: SAR 313.5K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation686,000462,35043,950506,300⁦74%⁩
Earthworks & foundations1,764,000719,50070,500790,000⁦45%⁩
Concrete & structural works3,038,000965,700103,3501,069,050⁦35%⁩
Mechanical, electrical & plumbing2,352,000470,55056,150526,700⁦22%⁩
Finishes & external works1,470,000187,75023,850211,600⁦14%⁩
Testing & commissioning490,00027,6503,70031,350⁦6%⁩
Total9,800,0002,833,500301,5003,135,000⁦32%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2026-09-13⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-09-15⁩

Project manager

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-09-18⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-09-21⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-09-24⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-09-13⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2026-09-15⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-09-18⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 3 days

  4. Payment order prepared⁦2026-09-21⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-09-24⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-09-24⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ibrahim A. Al-Ghamdi → Dr. Abdullah S. Al-Qahtani

Certificate history

24 September 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-09-24 13:00

21 September 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-09-21 13:00

18 September 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Project manager certifies”

    2026-09-18 13:00

15 September 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-09-15 13:00

13 September 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-09-13 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close