PRJ-2026-007 · From item 2
Training & Employment Centre ComplexPlanned to date 82%
- SPI
- 0.70
- Forecast finish
- 2027-06-01
- Budget
- SAR 32M
152 days lateMaterial risks: 3Open impediments: 4Corrective plan CP-2026-03
Change requests with complete files, week 43.
Held on
21 October 202613:00 – 14:10
60 of 60 min
Approve the previous minutes
ApprovalEng. Ibrahim A. Al-Ghamdi
5 min
Training complex — 150-day extension
DecisionEng. Shahad M. Al-Malki
30 min
Investment building — axes 12–16 foundation redesign
DecisionEng. Ahmed Y. Asiri
25 min
1. Approve the previous minutes
Meeting 40 minutes approved.
2. Training complex — 150-day extension
CR-2026-006Deferred pending the independent engineer; Finance abstained.
3. Investment building — axes 12–16 foundation redesign
CR-2026-010At SAR 420K on a revised baseline it exceeds the change committee’s authority; sent up to the Strategy & Projects Steering Committee.
Voting rule: Simple majority; a Finance objection on impact above SAR 250K sends it to the Strategy & Projects Steering Committee
Training complex extension decision deferred pending the independent engineer
DEC-2026-040Hold
For 4Against 0Abstain 1Carried
They show in the task register and on the owner’s calendar
No tasks from this meeting yet
Quorum: Four of six members, including Finance
At least 4 voting members needed
2 files
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
Shown only to invitees and the PMO, and leaves out what your permissions do not let you see.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
PRJ-2026-007 · From item 2
Training & Employment Centre ComplexPlanned to date 82%
152 days lateMaterial risks: 3Open impediments: 4Corrective plan CP-2026-03
PRJ-2026-020 · From item 3
The Chamber’s Investment Building — Business Tower on King Fahd RoadPlanned to date 55%
64 days lateMaterial risks: 1Open impediments: 1Corrective plan CP-2026-04
Agenda item needing a decision · CR-2026-006
Training complex — 150-day extensionFrom item 2
Agenda item needing a decision · CR-2026-010
Investment building — axes 12–16 foundation redesignFrom item 3
Change request awaiting decision · CR-2026-005
Variation 7: revise the central HVAC systemTraining & Employment Centre Complex
Corrective plan awaiting approval · CP-2026-03
Training & Employment Centre ComplexISS-0109 · Training & Employment Centre Complex
A decision· Asked from: Executive Committee
A decision to accept an equivalent façade alternative on the consultant’s advice, or to extend the supply period
CP-2026-03 · Training & Employment Centre Complex
A decision· Asked from: Executive Committee
A decision to accept an equivalent façade on the consultant’s advice
ACT-0311 · Eng. Ibrahim A. Al-Ghamdi