PRJ-2026-014 · From item 3
My Business Portal 2.0 — the Unified Member JourneyPlanned to date 67%
- SPI
- 0.87
- Forecast finish
- 2027-05-12
- Budget
- SAR 4.3M
42 days lateMaterial risks: 2Open impediments: 7Corrective plan CP-2026-01
Member Services & Business Voice portfolio review and the updated My Business Portal 2.0 corrective plan.
Scheduled for
10:002026-11-0323 Jumada I 1448 AH · 10:00
110 of 120 min
Approve the previous minutes
ApprovalDr. Noura M. Al-Otaibi
5 min
Member Services & Business Voice portfolio brief
DiscussionFaisal A. Al-Shehri
35 min
Updated corrective plan — My Business Portal 2.0
DecisionEng. Sultan F. Al-Ghamdi
35 min
Investment building foundation redesign
DecisionEng. Ahmed Y. Asiri
25 min
Any other business
DiscussionDr. Abdullah S. Al-Qahtani
10 min
What will be presented and what needs a decision — read before the meeting
Approve the previous minutes
ApprovalPresented by Dr. Noura M. Al-Otaibi5 min
Member Services & Business Voice portfolio brief
DiscussionPresented by Faisal A. Al-Shehri35 minPF-DT
Updated corrective plan — My Business Portal 2.0
DecisionPresented by Eng. Sultan F. Al-Ghamdi35 minCP-2026-01
Needs a committee decision
Investment building foundation redesign
DecisionPresented by Eng. Ahmed Y. Asiri25 minCR-2026-010
Needs a committee decision
Any other business
DiscussionPresented by Dr. Abdullah S. Al-Qahtani10 min
From this committee’s earlier meetings and decisions — reviewed at the start
ACT-0306 · Eng. Sultan F. Al-Ghamdi
ACT-0310 · Eng. Shahad M. Al-Malki
ACT-0323 · Faisal A. Al-Shehri
ACT-0324 · Rahaf I. Al-Nefaie
Quorum: Five of seven voting members, including the chair or vice-chair
At least 5 voting members needed
0 files
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
The summary is available once the meeting has been held and minuted.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
PRJ-2026-014 · From item 3
My Business Portal 2.0 — the Unified Member JourneyPlanned to date 67%
42 days lateMaterial risks: 2Open impediments: 7Corrective plan CP-2026-01
PRJ-2026-020 · From item 4
The Chamber’s Investment Building — Business Tower on King Fahd RoadPlanned to date 55%
64 days lateMaterial risks: 1Open impediments: 1Corrective plan CP-2026-04
Agenda item needing a decision · CP-2026-01
Updated corrective plan — My Business Portal 2.0From item 3
Agenda item needing a decision · CR-2026-010
Investment building foundation redesignFrom item 4
Change request awaiting decision · CR-2026-004
Add membership transfer & record merge to the first releaseMy Business Portal 2.0 — the Unified Member Journey
Corrective plan awaiting approval · CP-2026-01
My Business Portal 2.0 — the Unified Member JourneyISS-0103 · My Business Portal 2.0 — the Unified Member Journey
PeopleSAR 49K· Asked from: Change Committee
Three extra vendor integration engineers for four months through change request CR-2026-012
ISS-0101 · My Business Portal 2.0 — the Unified Member Journey
Coordination· Asked from: Dr. Abdullah S. Al-Qahtani
A letter from the Secretary-General to the National Information Center for a dedicated test environment for three months
CP-2026-01 · My Business Portal 2.0 — the Unified Member Journey
PeopleSAR 49K· Asked from: Change Committee
Approve change request CR-2026-012 for three integration engineers
Nothing