Programme · PG-10 · Institutional Excellence & Capability Portfolio

Institutional Excellence & Capability Programme

On track

Operational plans, performance measurement, the entrepreneurship fast track and the e-learning platform.

Approved budget
SAR 1.4M

incl. SAR 75K programme reserve

Actual spend
SAR 705K

⁦50%⁩ of budget

EAC
SAR 1.4M+0.5%

Estimate at completion

Progress
⁦54%⁩

Planned ⁦55%⁩

Schedule performance index
0.98

Cost performance index 1.00

Manager

Ghada A. Al-Shahrani

Director, Entrepreneurship & Young Businesspeople

Sponsor

Dr. Amal F. Al-Sudairi

Director General, Strategy & the PMO

Projects

4 projects

2025-09-07 — 2027-12-31

On track 3At risk 1

Programme objectives

What the programme must achieve, and the strategic objectives it serves.

  1. 1

    Approved operational plans for the chamber’s 2025–2030 strategy, turned into portfolios and initiatives

  2. 2

    Raise PMO maturity to 3.5 out of 5

  3. 3

    25% of relevant chamber staff through specialist development tracks

Programme benefits

From baseline to target

  • PMO maturity index

    by ⁦2027⁩
    Baseline 2.4Current 3.2 of 5Target 3.5
  • Employee engagement index

    by ⁦2027⁩
    Baseline 66Current 71 %Target 75

Roadmap

One lane per project: start to forecast finish, with the progress earned and the baseline finish.

EarnedRemainingBaseline finishSlip
202520262027
2026-12-24
2027-01-31
2026-12-15
2027-12-31

Dependencies between projects

What waits on what. Red links are on the programme’s critical path.

Critical path

What each project needs from the one before

  • The Power BI performance dashboards are built on the new operational plans’ KPIs

  • Fast Track targets are derived from the entrepreneurship operational plan

  • The e-learning platform hosts the Fast Track programmes for entrepreneurs

Shared risks

Risks that hit more than one project, managed at programme level.

6

A late operational-plan approval delays the new performance KPIs

PRK-10-1·Accept·Abeer H. Al-Shamrani

Affects

Open risks in the programme’s projects

1 risk

Open risks in the programme’s projects
  • Critical0
  • High0
  • Medium1
  • Low0
  • Risks 1
Probability
5
4
3
2
1
12345

Impact

Open risks in the programme’s projects
Probability \ Impact12345
50 · Low0 · Medium0 · High0 · Critical0 · Critical
40 · Low0 · Medium0 · Medium0 · High0 · Critical
30 · Low0 · Low1 · Medium0 · Medium0 · High
20 · Low0 · Low0 · Low0 · Medium0 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Programme KPIs · Stakeholders

Stakeholders

Power against interest; click a person to see their role.

Power

Keep satisfied0

Manage closely4

Monitor0

Keep informed0

Dr. Amal F. Al-SudairiManage closelyDr. Abdullah S. Al-QahtaniManage closelyDr. Noura M. Al-OtaibiManage closelyAbdulmajeed R. Al-DosariManage closely

Interest

Programme decisions

What the committees decided on the programme’s projects, and what the programme raised to them.

Committees

Executive Committee

Weekly · Quorum ⁦4⁩

Dr. Mohammed I. Al-Subaie · Executive Director, Strategy & Institutional ExcellenceEng. Turki A. Al-Anazi · Executive Director, Training & Employment CentreEng. Majed S. Al-Rasheed · Executive Director, Digital Transformation & ITSarah A. Al-Qarni · Assistant Secretary-General, Support Services
Chair: Dr. Abdullah S. Al-QahtaniNext meeting 2026-10-28
Project Approval Committee

Fortnightly · Quorum ⁦4⁩

Faisal A. Al-Shehri · Director General, Digital Services & Portfolio Manager, Digital Services & Member ExperienceDr. Amal F. Al-Sudairi · Director General, Strategy & the PMOTariq S. Al-Yami · Head, Institutional Performance & Quality
Chair: Dr. Noura M. Al-OtaibiNext meeting 2026-11-04

Programme projects

The programme’s performance is computed from these projects.

⁦4⁩ results
Export CSV
Manager
Institutional Performance Measurement & Power BI DashboardsPRJ-2026-012Tariq S. Al-Yami4ExecutionOn track⁦76%⁩490K490K⁦0.0%⁩1.01Schedule performance index · 1.011.00Cost performance index · 1.00
Entrepreneurship Fast Track PlatformPRJ-2026-027Ghada A. Al-Shahrani4ExecutionAt risk⁦63%⁩320K327K⁦+2.2%⁩0.88Schedule performance index · 0.880.98Cost performance index · 0.98
Operational Plans & Scorecards for the 2025–2030 StrategyPRJ-2026-028Abeer H. Al-Shamrani4ExecutionOn track⁦70%⁩160K160K⁦0.0%⁩1.03Schedule performance index · 1.031.00Cost performance index · 1.00
Training Centre e-Learning PlatformPRJ-2026-029Ghada A. Al-Shahrani3PlanningOn track⁦4%⁩375K375K⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Total · 41.3M1.4M
⁦1⁩–⁦4⁩ of ⁦4⁩

Budget shares

Budget shares

SAR 1.3M

Budget

  • Institutional Performance Measurement & Power BI DashboardsSAR 490K⁦36%⁩
  • Entrepreneurship Fast Track PlatformSAR 320K⁦24%⁩
  • Operational Plans & Scorecards for the 2025–2030 StrategySAR 160K⁦12%⁩
  • Training Centre e-Learning PlatformSAR 375K⁦28%⁩
Budget shares
CategoryValueShare
Institutional Performance Measurement & Power BI DashboardsSAR 490K⁦36%⁩
Entrepreneurship Fast Track PlatformSAR 320K⁦24%⁩
Operational Plans & Scorecards for the 2025–2030 StrategySAR 160K⁦12%⁩
Training Centre e-Learning PlatformSAR 375K⁦28%⁩
TotalSAR 1.3M⁦100%⁩