A late operational-plan approval delays the new performance KPIs
PRK-10-1·Accept·Abeer H. Al-Shamrani
Programme · PG-10 · Institutional Excellence & Capability Portfolio
Operational plans, performance measurement, the entrepreneurship fast track and the e-learning platform.
incl. SAR 75K programme reserve
50% of budget
Estimate at completion
Planned 55%
Cost performance index 1.00
Manager
Ghada A. Al-Shahrani
Director, Entrepreneurship & Young Businesspeople
Sponsor
Dr. Amal F. Al-Sudairi
Director General, Strategy & the PMO
Projects
4 projects
2025-09-07 — 2027-12-31
On track 3At risk 1
What the programme must achieve, and the strategic objectives it serves.
Approved operational plans for the chamber’s 2025–2030 strategy, turned into portfolios and initiatives
Raise PMO maturity to 3.5 out of 5
25% of relevant chamber staff through specialist development tracks
From baseline to target
PMO maturity index
by 2027Employee engagement index
by 2027One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
The Power BI performance dashboards are built on the new operational plans’ KPIs
Fast Track targets are derived from the entrepreneurship operational plan
The e-learning platform hosts the Fast Track programmes for entrepreneurs
Risks that hit more than one project, managed at programme level.
A late operational-plan approval delays the new performance KPIs
PRK-10-1·Accept·Abeer H. Al-Shamrani
1 risk
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 0 · Critical | 0 · Critical |
| 4 | 0 · Low | 0 · Medium | 0 · Medium | 0 · High | 0 · Critical |
| 3 | 0 · Low | 0 · Low | 1 · Medium | 0 · Medium | 0 · High |
| 2 | 0 · Low | 0 · Low | 0 · Low | 0 · Medium | 0 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
PMO maturity index
3.2out of 5
0
Target 3.591%
Trainees on the training centre’s programmes (cumulative)
1,810trainees
+230
Target 2,40075%
Start-ups served by the Entrepreneurship Fast Track (cumulative)
185businesses
+20
Target 20093%
Projects compliant with the delivery methodology
84%
+2
Target 90%93%
Power against interest; click a person to see their role.
Keep satisfied0
Manage closely4
Monitor0
Keep informed0
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
Committees
Weekly · Quorum 4
Fortnightly · Quorum 4
Members
7 members
The programme’s performance is computed from these projects.
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| Institutional Performance Measurement & Power BI DashboardsPRJ-2026-012 | Tariq S. Al-Yami | 4Execution | On track | 76% | 490K | 490K0.0% | 1.01Schedule performance index · 1.01 | 1.00Cost performance index · 1.00 |
| Entrepreneurship Fast Track PlatformPRJ-2026-027 | Ghada A. Al-Shahrani | 4Execution | At risk | 63% | 320K | 327K+2.2% | 0.88Schedule performance index · 0.88 | 0.98Cost performance index · 0.98 |
| Operational Plans & Scorecards for the 2025–2030 StrategyPRJ-2026-028 | Abeer H. Al-Shamrani | 4Execution | On track | 70% | 160K | 160K0.0% | 1.03Schedule performance index · 1.03 | 1.00Cost performance index · 1.00 |
| Training Centre e-Learning PlatformPRJ-2026-029 | Ghada A. Al-Shahrani | 3Planning | On track | 4% | 375K | 375K0.0% | 1.00Schedule performance index · 1.00 | 1.00Cost performance index · 1.00 |
| Total · 4 | 1.3M | 1.4M |
SAR 1.3M
Budget
| Category | Value | Share |
|---|---|---|
| Institutional Performance Measurement & Power BI Dashboards | SAR 490K | 36% |
| Entrepreneurship Fast Track Platform | SAR 320K | 24% |
| Operational Plans & Scorecards for the 2025–2030 Strategy | SAR 160K | 12% |
| Training Centre e-Learning Platform | SAR 375K | 28% |
| Total | SAR 1.3M | 100% |