Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-003At risk4ExecutionWaterfallIn progress

Disaster Recovery Centre for the Chamber’s Systems

Add to watchlist

A Tier III standby site at a licensed provider in Al-Kharj that keeps the My Business portal, e-attestation and the chamber’s systems running after a major outage.

Early warning: ⁦63%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 7.4M

Actual cost

SAR 5.9M

⁦79%⁩ of budget

Progress

⁦72%⁩Awaiting acceptance ⁦8%⁩

Estimate at completion

SAR 8.1M

SAR +732K

SPI · CPI

0.90Schedule performance index · 0.900.91Cost performance index · 0.91

Forecast finish

⁦2027-01-07⁩

38 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 February 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate6 April 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate11 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 October 2026Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
RC-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2025-08-04⁩
Hijri
10 Safar 1447 AH
ApprovedCRT-003-01Project plan & baseline

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-003
Project
Disaster Recovery Centre for the Chamber’s Systems
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation & IT
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Eng. Omar H. Bawazir

1The deliverableAuto-filled

DeliverableAuto-filled
Project plan & baseline
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Eng. Omar H. Bawazir
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦5%⁩
DueAuto-filled
⁦2025-06-28⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-003_1.1_v1.pdfV1Eng. Omar H. Bawazir⁦2025-04-06⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Eng. Nayef H. Al-Buqami
Accepted byAuto-filled
Eng. Majed S. Al-Rasheed
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Project plan approved
ContractAuto-filled
CTR-2025-006
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Omar H. BawazirDirector, IT InfrastructureSubmitted—⁦2025-04-06⁩ 13:34
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-04-07⁩ 11:50
3Inspection & technical acceptance — ownerTechnical acceptanceEng. Majed S. Al-RasheedProject ownerOn behalf of Eng. Nayef H. Al-BuqamiApprovedInspected and accepted against the approved acceptance criteria.⁦2025-04-08⁩ 12:57
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-04-10⁩ 10:37
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-04-13⁩ 11:14

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2025-04-07⁩

Inspection & technical acceptance — owner

Eng. Majed S. Al-Rasheed

Approved⁦2025-04-08⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2025-04-10⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2025-04-13⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Eng. Omar H. Bawazir on ⁦2025-04-06⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-04-07⁩ at ⁦11:50⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Eng. Nayef H. Al-Buqami · Project owner

    Approved · ⁦2025-04-08⁩ at ⁦12:57⁩ · On behalf of Eng. Nayef H. Al-Buqami (Eng. Majed S. Al-Rasheed)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-04-10⁩ at ⁦10:37⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-04-13⁩ at ⁦11:14⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-04-06⁩

    PRJ-2026-003_1.1_v1.pdf

    Eng. Omar H. Bawazir

Only one version so far.