Disaster Recovery Centre for the Chamber’s Systems
Add to watchlist
A Tier III standby site at a licensed provider in Al-Kharj that keeps the My Business portal, e-attestation and the chamber’s systems running after a major outage.
Early warning: 63% chance of slipping within 45 days
Budget (BAC)
SAR 7.4M
Actual cost
SAR 5.9M
79% of budget
Progress
72%Awaiting acceptance 8%
Estimate at completion
SAR 8.1M
SAR +732K
SPI · CPI
0.90Schedule performance index · 0.900.91Cost performance index · 0.91
Forecast finish
2027-01-07
38 days behind baseline
Execution·Stage 4 of 5
Next gate:Closure13 October 2026
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate5 February 2025Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionConditional goDate6 April 2025Planning · CompletePlanning · Complete
Gate into «Execution»DecisionConditional goDate11 July 2025Execution · Current stageExecution · Current stage
Gate into «Closure»DecisionNot held yetDate13 October 2026Closure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+40 days vs approved
Baseline (original = approved)2026-11-30
Current forecast2027-01-09
By earned schedule2027-09-03
Critical activities
5
of 6 open activities
Late activities
4
past their baseline finish
Schedule performance
0.73
earned ÷ planned value
Next milestone
in 41 days
Testing & acceptance complete
Layers
Compare with
Expand allCollapse all
ActivityOwnerForecast finishProgress
2025
2026
2027
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
Today
2027-01-0972%
Disaster Recovery Centre for the Chamber’s SystemsPlanned: 2025-04-06 → 2026-11-30Forecast: 2025-04-06 → 2027-01-09Float: 0d