PRJ-2026-006Off track4ExecutionConstructionStalled

Chamber Branch & Manufacturers’ Service Centre — Second Industrial City

Remove from watchlist

A full branch serving the factories of the Second Industrial City — membership, attestation and certificates of origin — with 40 service desks and training rooms; it needs ground improvement and Riyadh Region Municipality permits.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 14.3M

Actual cost

SAR 6.3M

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 16.1M

SAR +1.8M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started

Project charter

Objective, scope, deliverables, roles and budget

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Initiation

Project charter

Objective, scope, deliverables, roles and budget

Form no.
RC-PMO-F04
Template edition
3.0
Version
V2
Form date
⁦2024-08-30⁩
Hijri
26 Safar 1446 AH
ApprovedPRJ-2026-006Chamber Branch & Manufacturers’ Service Centre — Second Industrial City

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-006
Project
Chamber Branch & Manufacturers’ Service Centre — Second Industrial City
Portfolio
Branches, Service & Training Centres Portfolio
Sector
Member Experience & Business Development Sector
Sponsor
Eng. Sami A. Al-Fraih
Project manager
Eng. Fahad T. Al-Sulami

1Objective

Background

A full branch serving the factories of the Second Industrial City — membership, attestation and certificates of origin — with 40 service desks and training rooms; it needs ground improvement and Riyadh Region Municipality permits.

Project objectives

  1. The chamber’s services across Riyadh city and its governorates
  2. A better member experience and service quality

2Scope

In scope

  • A full branch serving the factories of the Second Industrial City — membership, attestation and certificates of origin — with 40 service desks and training rooms; it needs ground improvement and Riyadh Region Municipality permits.
  • Saudi Building Code compliance
  • Consultant-approved drawings

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

3Deliverables and milestones

DeliverableDue
Project management plan⁦2024-10-09⁩
Main deliverable — stage 1⁦2025-12-25⁩
Main deliverable — final stage⁦2026-11-19⁩
Final report⁦2027-03-31⁩
MilestoneDate
Charter approved⁦2024-08-30⁩
Contract signed⁦2025-01-30⁩
50% of works complete⁦2025-12-25⁩
Provisional acceptance⁦2027-01-15⁩
Closure⁦2027-03-31⁩

4RolesAuto-filled

SponsorAuto-filled
Eng. Sami A. Al-Fraih
Project ownerAuto-filled
Eng. Bandar M. Al-Shammari
Project managerAuto-filled
Eng. Fahad T. Al-Sulami
StakeholderRole
Project sponsorDecisions and funding
Project ownerAccepts deliverables, owns benefits
Project Management Office (PMO)Governance and compliance
Governance bodyRoleCadence
Change CommitteeApproves scope, cost and schedule changesWeekly
PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly

5BudgetAuto-filled

LineAmount
Main contractSAR 10.3M
Supervision & consultingSAR 2M
Internal teamSAR 1.3M
Contingency reserve (5%)SAR 715K
Approved budgetSAR 14.3M

Funding

The owning sector’s approved budget

6Success criteria and constraints

Success criteria

  • Delivered within the approved budget
  • On the approved date ±5%
  • Target benefits within 12 months

Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

Assumptions

  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

Approval logChain: Project charter approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresSubmitted—⁦2024-08-21⁩ 10:00
2PMO complianceMethodology reviewDr. Noura M. Al-OtaibiPMO — directorApproved—⁦2024-08-24⁩ 12:30
3Project ownerTechnical acceptanceEng. Bandar M. Al-ShammariProject ownerApproved—⁦2024-08-27⁩ 09:45
4Budget funding confirmedFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2024-08-28⁩ 11:10
5Sponsor approvalTechnical acceptanceEng. Sami A. Al-FraihProject sponsorApproved—⁦2024-08-30⁩ 11:00

Signatures

PMO compliance

Dr. Noura M. Al-Otaibi

Approved⁦2024-08-24⁩

Project owner

Eng. Bandar M. Al-Shammari

Approved⁦2024-08-27⁩

Budget funding confirmed

Munirah A. Al-Khalidi

Approved⁦2024-08-28⁩

Sponsor approval

Eng. Sami A. Al-Fraih

Approved⁦2024-08-30⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F04 · version V2

Project charter

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project charter approval · version ⁦1⁩

Submitted by Eng. Fahad T. Al-Sulami on ⁦2024-08-21⁩

  1. Methodology review

    PMO compliance

    Dr. Noura M. Al-Otaibi · PMO — director

    Approved · ⁦2024-08-24⁩ at ⁦12:30⁩

  2. Technical acceptance

    Project owner

    Eng. Bandar M. Al-Shammari · Project owner

    Approved · ⁦2024-08-27⁩ at ⁦09:45⁩

  3. Financial approval

    Budget funding confirmed

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2024-08-28⁩ at ⁦11:10⁩

  4. Technical acceptance

    Sponsor approval

    Eng. Sami A. Al-Fraih · Project sponsor

    Approved · ⁦2024-08-30⁩ at ⁦11:00⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-08-30⁩

    Approved version

    • PMO comments addressed

    Eng. Fahad T. Al-Sulami

  2. V1Returned for edit⁦2024-08-11⁩

    First draft

    • Returned to detail the budget

    Eng. Fahad T. Al-Sulami