Planning
Kick-off meeting minutes
Roles, tasks, decisions and the start of execution
- Form no.
- RC-PMO-F06
- Template edition
- 1.2
- Version
- V1
- Form date
- 2024-09-08
- Hijri
- 5 Rabiʻ I 1446 AH
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-006
- Project
- Chamber Branch & Manufacturers’ Service Centre — Second Industrial City
- Portfolio
- Branches, Service & Training Centres Portfolio
- Sector
- Member Experience & Business Development Sector
- Sponsor
- Eng. Sami A. Al-Fraih
- Project manager
- Eng. Fahad T. Al-Sulami
1The meetingAuto-filled
- MeetingAuto-filled
- Kick-off — Chamber Branch & Manufacturers’ Service Centre — Second Industrial City
- Date and timeAuto-filled
- 2024-09-08 · 10:00
- PlaceAuto-filled
- Main meeting room — headquarters
- SecretaryAuto-filled
- Eng. Fahad T. Al-Sulami
Purpose
Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.
| Attendees | Title |
|---|---|
| Eng. Sami A. Al-Fraih | Assistant Secretary-General, Member Experience & Business Development |
| Eng. Bandar M. Al-Shammari | Director General, Facilities & General Services |
| Eng. Fahad T. Al-Sulami | Senior Project Manager — Branches & Service Centres |
| Dr. Noura M. Al-Otaibi | Director, Project Management Office |
| Eng. Abdulrahman S. Al-Harbi | Director General, Training & Entrepreneurship |
2Roles
| Person | Role | Duty |
|---|---|---|
| Eng. Sami A. Al-Fraih | Project sponsor | Sponsors the project, decides escalations and material changes |
| Eng. Bandar M. Al-Shammari | Project owner | Approves the requirements and accepts the deliverables |
| Eng. Fahad T. Al-Sulami | Project manager | Runs the plan, deliverables and risks; files the periodic update card |
| Dr. Noura M. Al-Otaibi | Project Management Office | Follows the methodology and checks the periodic updates |
| Eng. Abdulrahman S. Al-Harbi | Training lead on the branch’s hall design | Delivers their tasks and uploads the evidence |
3Tasks
| Task | Owner | Due | Status |
|---|---|---|---|
| Project plan approved | Eng. Fahad T. Al-Sulami | 2025-03-14 | Done |
| Designs approved | Eng. Fahad T. Al-Sulami | 2025-08-11 | Done |
| Build complete | Eng. Fahad T. Al-Sulami | 2026-03-23 | Open |
| Testing & acceptance complete | Eng. Fahad T. Al-Sulami | 2026-11-02 | Open |
4Decisions
- The charter is the reference for scope, budget and the milestone plan
- Change Committee: Approves scope, cost and schedule changes (Weekly)
- PMO Committee: Methodology compliance, data quality, stage gates (Fortnightly)
- The periodic update card monthly, before the 5th of the month
5Start of execution
- Execution starts on
- 2025-01-30
- Start confirmed
- Eng. Sami A. Al-Fraih · 2024-09-09
Approval logChain: Kick-off minutes approval · version 1
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service Centres | Submitted | — | 2024-09-09 11:56 |
| 2 | Minutes against the template | Methodology review | Ghada A. Al-ShahraniPMO — analyst | Approved | — | 2024-09-10 09:00 |
| 3 | Chair’s approval (sponsor) | Technical acceptance | Eng. Sami A. Al-FraihProject sponsor | Approved | — | 2024-09-10 12:30 |
Signatures
Minutes against the template
Ghada A. Al-Shahrani
Approved2024-09-10
Chair’s approval (sponsor)
Eng. Sami A. Al-Fraih
Approved2024-09-10