Chamber Branch & Manufacturers’ Service Centre — Second Industrial City
Remove from watchlistA full branch serving the factories of the Second Industrial City — membership, attestation and certificates of origin — with 40 service desks and training rooms; it needs ground improvement and Riyadh Region Municipality permits.
Budget (BAC)
Actual cost
44% of budget
Progress
Estimate at completion
SAR +1.8M
SPI · CPI
Forecast finish
95 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure15 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-03-14 | 2025-09-02 | +172 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-08-11 | 2026-06-10 | +303 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-03-23 | 2027-01-11 | +294 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.sa | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-11-02 | 2027-04-23 | +172 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-03-31 | 2027-06-30 | +91 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
39%Awaiting acceptance
11%Not handed in
50%Deliverable flow
Display options
| Project plan & baseline006-D1 | 4% | CRT-006-01 | Approved | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.sa | Eng. Bandar M. Al-Shammari | 2024-12-29 | V1 | 3 of 3 |
| Monitoring & reporting006-D2 | 4% | CRT-006-02 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-03-14 | V1 | 3 of 3 |
| Detailed design006-D3 | 8% | CRT-006-03 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-05-28 | V1 | 3 of 3 |
| Permits & approvals006-D4 | 7% | CRT-006-04 | Approved | Eng. Sami A. Al-FraihEng. Sami A. Al-FraihAssistant Secretary-General, Member Experience & Business DevelopmentP-049s.alfraih@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-08-11 | V1 | 3 of 3 |
| Site works & excavation006-D5 | 16% | CRT-006-05 | Approved | Eng. Sami A. Al-FraihEng. Sami A. Al-FraihAssistant Secretary-General, Member Experience & Business DevelopmentP-049s.alfraih@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-10-24 | V1 | 3 of 3 |
| Structure006-D6 | 11% | — | Under review | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-01-07 | V1 | 1 of 3 |
| Finishes006-D7 | 11% | — | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-03-23 | V0 | 0 of 3 |
| Supply006-D8 | 9% | — | Draft | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-06-05 | V0 | 0 of 3 |
| Installation006-D9 | 9% | — | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-08-19 | V0 | 0 of 3 |
| Testing & commissioning006-D10 | 9% | — | Draft | Eng. Sami A. Al-FraihEng. Sami A. Al-FraihAssistant Secretary-General, Member Experience & Business DevelopmentP-049s.alfraih@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-11-02 | V0 | 0 of 3 |
| Provisional acceptance006-D11 | 6% | — | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2027-01-15 | V0 | 0 of 3 |
| Final acceptance006-D12 | 6% | — | Draft | Eng. Sami A. Al-FraihEng. Sami A. Al-FraihAssistant Secretary-General, Member Experience & Business DevelopmentP-049s.alfraih@chamber.sa | Eng. Bandar M. Al-Shammari | 2027-03-31 | V0 | 0 of 3 |
| Total · 12 | 100% |