PRJ-2026-010On track4ExecutionConstructionIn progress

Solar Power for the Chamber’s Buildings & Branches

Add to watchlist

6 MW of rooftop and carport solar on 14 buildings and branches, the largest array at the training centre complex.

Budget (BAC)

SAR 4.8M

Actual cost

SAR 2.8M

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 4.8M

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work4.7M⁦17⁩ elements
Unallocated contingency144KSAR 240K
Budget at completion4.8MPRJ-2026-010
Weighted progress⁦58%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project789⁦2025-03-02⁩⁦2027-04-30⁩⁦58%⁩4.662.76—
1
Phase207⁦2025-03-02⁩⁦2025-09-25⁩⁦100%⁩0.280.29—
1.1
WBS element127⁦2025-03-02⁩⁦2025-07-07⁩⁦100%⁩0.140.140 / 1
1.2
WBS element127⁦2025-05-21⁩⁦2025-09-25⁩⁦100%⁩0.140.141 / 2
2
Phase207⁦2025-08-08⁩⁦2026-03-03⁩⁦100%⁩0.560.57—
2.1
WBS element128⁦2025-08-08⁩⁦2025-12-14⁩⁦100%⁩0.280.291 / 1
2.2
WBS element127⁦2025-10-27⁩⁦2026-03-03⁩⁦100%⁩0.280.291 / 2
3
Phase285⁦2026-01-14⁩⁦2026-10-26⁩⁦100%⁩1.771.81—
3.1
WBS element128⁦2026-01-14⁩⁦2026-05-22⁩⁦100%⁩0.590.601 / 1
3.2
WBS element127⁦2026-04-04⁩⁦2026-08-09⁩⁦100%⁩0.590.601 / 1
3.3
WBS element125⁦2026-06-23⁩⁦2026-10-26⁩⁦100%⁩0.590.601 / 2
4
Phase295⁦2026-05-14⁩⁦2027-03-05⁩⁦7%⁩1.400.10—
4.1
WBS element247⁦2026-05-14⁩⁦2027-01-16⁩⁦20%⁩0.470.101 / 1
4.2
WBS element38⁦2027-01-02⁩⁦2027-02-09⁩⁦0%⁩0.47—1 / 1
4.3
WBS element38⁦2027-01-26⁩⁦2027-03-05⁩⁦0%⁩0.47—1 / 2
5
Phase70⁦2027-02-19⁩⁦2027-04-30⁩⁦0%⁩0.65——
5.1
WBS element38⁦2027-02-19⁩⁦2027-03-29⁩⁦0%⁩0.33—1 / 1
5.2
WBS element38⁦2027-03-15⁩⁦2027-04-22⁩⁦0%⁩0.33—1 / 1
Total⁦58%⁩4.662.76