Execution
Change request
The change, its impact analysis and the approval decision
- Form no.
- RC-PMO-F09
- Template edition
- 3.1
- Version
- V1
- Form date
- 2026-09-28
- Hijri
- 17 Rabiʻ II 1448 AH
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-020
- Project
- The Chamber’s Investment Building — Business Tower on King Fahd Road
- Portfolio
- New Headquarters & Investment Assets Portfolio
- Sector
- Investment Department
- Sponsor
- Sarah A. Al-Qarni
- Project manager
- Eng. Ahmed Y. Asiri
1The change
- TitleAuto-filled
- Redesign the foundations of axes 12 to 16
- KindAuto-filled
- Scope
- Requested byAuto-filled
- Eng. Ahmed Y. Asiri
- Raised onAuto-filled
- 2026-09-28
Reason
Unforeseen ground at axes 12 to 16
Justification
The current design misses the required safety factor
2Impact analysis
Cost
SAR +420K
Schedule
+55 days
Risk
20 → 8
Benefits
0%
Risk impact
Treats the investment building’s critical risk
Benefits impact
No effect on benefits
3The approval decision
The PMO’s recommendation
The PMO recommends urgent approval: every day of delay costs SAR 7.5K
- Change Committee decision
- Not taken yet
- Decided on
- —
- Decision number
- —
Approval logChain: Change request approval · version 5
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Ahmed Y. AsiriDirector, Construction Projects & Buildings | Submitted | — | 2026-09-28 10:49 |
| 2 | Project manager | Technical acceptance | Eng. Ahmed Y. AsiriProject manager | Approved | — | 2026-09-29 12:03 |
| 3 | PMO review & impact analysis | Methodology review | Ghada A. Al-ShahraniPMO — analyst | Approved | — | 2026-09-30 13:10 |
| 4 | Financial impact | Financial approval | Approval engineFinance | Pre-breach alert | — | 2026-10-04 08:00 |
Signatures
Project manager
Eng. Ahmed Y. Asiri
Approved2026-09-29
PMO review & impact analysis
Ghada A. Al-Shahrani
Approved2026-09-30
Financial impact
Munirah A. Al-Khalidi
Awaiting decision
Contractual impact
Mazen A. Al-Hazmi
Later
Change Committee
Dr. Mohammed I. Al-Subaie
Later