PRJ-2026-020Off track4ExecutionConstructionStalled

The Chamber’s Investment Building — Business Tower on King Fahd Road

Remove from watchlist

A 22-storey office tower on chamber-owned land to diversify non-membership revenue; the foundations of axes 12–16 face high groundwater.

Early warning: ⁦81%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 17.3M

Actual cost

SAR 8M

⁦46%⁩ of budget

Progress

⁦44%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 18.2M

SAR +908K

SPI · CPI

0.80Schedule performance index · 0.800.95Cost performance index · 0.95

Forecast finish

⁦2027-08-03⁩

64 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure5 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started

Project documents by stage

What each stage requires under the RFP, what has been filed and what is missing, and the evidence tied to deliverables.

Open in the repository
  • ⁦0⁩ of ⁦7⁩ mandatory documents due
  • 7 mandatory documents missing
  • 1 document in the repository

Documents in the project folder

Archived automatically when the project closes, and kept read-only under the retention policy.

Stages and required documents

For each of the five stages, what its gates and forms require: present, missing, or not yet due.

  1. 1Pre-start
    • Project proposal & feasibility studyMandatory· Missing

      Approval gate G1

    • Priority & weight assessmentOptional· Missing

      Annual work plan

  2. 2Initiation
    • Approved project charterMandatory· Missing

      Initiation gate G2

    • Kick-off meeting minutesMandatory· Missing

      Initiation gate G2

  3. 3Planning
  4. 4ExecutionCurrent stage
    • Periodic update cards & status reportsMandatory· Missing

      Periodic update card form

    • Deliverable completion certificatesMandatory· Missing

      Deliverable completion certificate form

    • Corrective plan when off trackOptional· Missing

      Corrective plan form

  5. 5Closure
    • Project closure & handover formMandatory· Not yet due

      Closure gate G4

    • Lessons learnedMandatory· Not yet due

      Closure gate G4

    • Acceptance test resultsOptional· Not yet due

      Deliverable acceptance

Documents linked to stages and tasks

Each document is tied to its stage of the project lifecycle and to the plan activities it serves — pick an activity to open it on the schedule

Project documents1
Linked to tasks0
Tasks with documents0

Evidence tied to deliverables

Each deliverable with its repository document and the files that prove it.

  • 020-D1Project plan & baselinePRJ-2026-020_1.1_v1.pdfApprovedDeliverable
  • 020-D2Monitoring & reportingPRJ-2026-020_1.2_v1.pdfApprovedDeliverable
  • 020-D3Detailed designPRJ-2026-020_2.1_v1.pdfApprovedDeliverable
  • 020-D4Permits & approvalsPRJ-2026-020_2.2_v1.pdfApprovedDeliverable
  • 020-D5Site works & excavationPRJ-2026-020_3.1_v1.pdfApprovedDeliverable
  • 020-D6StructurePRJ-2026-020_3.2_v1.pdfApprovedDeliverable
  • 020-D7FinishesPRJ-2026-020_3.3_v1.pdfIn reviewDeliverable
  • 020-D8SupplyNo evidence filed yetDraftDeliverable
  • 020-D9InstallationNo evidence filed yetDraftDeliverable
  • 020-D10Testing & commissioningNo evidence filed yetDraftDeliverable
  • 020-D11Provisional acceptanceNo evidence filed yetDraftDeliverable
  • 020-D12Final acceptanceNo evidence filed yetDraftDeliverable