PRJ-2026-020Off track4ExecutionConstructionStalled

The Chamber’s Investment Building — Business Tower on King Fahd Road

Remove from watchlist

A 22-storey office tower on chamber-owned land to diversify non-membership revenue; the foundations of axes 12–16 face high groundwater.

Early warning: ⁦81%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 17.3M

Actual cost

SAR 8M

⁦46%⁩ of budget

Progress

⁦44%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 18.2M

SAR +908K

SPI · CPI

0.80Schedule performance index · 0.800.95Cost performance index · 0.95

Forecast finish

⁦2027-08-03⁩

64 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure5 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 17.3M split into spent, committed and left, with the estimate at completion

Forecast overrun SAR 908K
EAC SAR 18.2M
Revised request SAR 17.7M
  • Actual spendSAR 8M
  • Committed, not spentSAR 7.8M
  • Allotted, uncommittedSAR 932.5K
  • Contingency availableSAR 517.5K

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 16.4M
Original budgetwhen the first baseline was approved
SAR 17.3M
Approved budgetafter approved change requests
SAR 17.3M
Current budgetavailable to spend now
SAR 17.3M
Revised budgetif the pending changes are approved
SAR 17.7M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 15.8M
Contracts2 active contracts
SAR 15.4M
Purchase orders⁦3⁩ orders
SAR 430K
Remaining budgetapproved less actual
SAR 9.3M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 8M
Accrualswork done, not yet invoiced
SAR 320K
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 18.2M
ContingencySAR 345.5K drawn of SAR 863K
SAR 517.5K

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 16.4M
ApprovedSAR 17.3M
Estimate at completionSAR 18.2M
Approved is SAR 860K (⁦5.2%⁩) above the estimate
The estimate at completion is SAR 1.8M (⁦10.8%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2024-03-19⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-90020
  • WBS elements⁦5⁩ elements · P-2026-020.01 …
  • Purchase orders⁦3⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦36⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 345.5K drawn of SAR 863K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 345.5K

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance1.001.091.091.09⁦−0.09⁩
2Design & permits2.012.182.182.18⁦−0.17⁩
3Civil works6.366.144.726.52⁦−0.16⁩
4MEP works5.024.360.005.53⁦−0.51⁩
5Handover2.342.030.002.58⁦−0.24⁩
Unallocated contingency0.520.000.000.26⁦+0.26⁩
Total17.2515.807.9918.16⁦−0.91⁩

Budget split

WBS

SAR 17.3M

Budget

  • Management & governanceSAR 1M⁦6%⁩
  • Design & permitsSAR 2M⁦12%⁩
  • Civil worksSAR 6.4M⁦37%⁩
  • MEP worksSAR 5M⁦29%⁩
  • HandoverSAR 2.3M⁦14%⁩
  • Unallocated contingencySAR 517.5K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2029-08-30⁩+822

SPI(t) ⁦0.57⁩ against the approved finish ⁦2027-05-31⁩

Planned valuePV
SAR 15.5M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 7.6M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 8M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 17.3M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦−0.40⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−7.96⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
0.95
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.49
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 18.2M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 10.2M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦−0.91⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.04
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 18.2M
  • If the rest goes to planSAR 17.6M
  • At cost and schedule performanceSAR 28.8M
  • The PM’s bottom-up estimateSAR 18.2M
  • To stay within SAR 17.3M, cost performance on the rest must rise to ⁦1.04⁩ — above what has been achieved.

Estimate at completion at that performance

SAR 18.2M

Variance at completion: ⁦−0.91⁩ SAR M