PRJ-2026-020Off track4ExecutionConstructionStalled

The Chamber’s Investment Building — Business Tower on King Fahd Road

Remove from watchlist

A 22-storey office tower on chamber-owned land to diversify non-membership revenue; the foundations of axes 12–16 face high groundwater.

Early warning: ⁦81%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 17.3M

Actual cost

SAR 8M

⁦46%⁩ of budget

Progress

⁦44%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 18.2M

SAR +908K

SPI · CPI

0.80Schedule performance index · 0.800.95Cost performance index · 0.95

Forecast finish

⁦2027-08-03⁩

64 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure5 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work16.7M⁦17⁩ elements
Unallocated contingency517.5KSAR 863K
Budget at completion17.3MPRJ-2026-020
Weighted progress⁦44%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project1,155⁦2024-06-02⁩⁦2027-08-01⁩⁦44%⁩16.737.99—
1
Phase346⁦2024-06-02⁩⁦2025-05-14⁩⁦100%⁩1.001.09—
1.1
WBS element213⁦2024-06-02⁩⁦2025-01-01⁩⁦100%⁩0.500.550 / 1
1.2
WBS element213⁦2024-10-13⁩⁦2025-05-14⁩⁦100%⁩0.500.551 / 2
2
Phase345⁦2025-02-23⁩⁦2026-02-03⁩⁦100%⁩2.012.18—
2.1
WBS element213⁦2025-02-23⁩⁦2025-09-24⁩⁦100%⁩1.001.091 / 1
2.2
WBS element212⁦2025-07-06⁩⁦2026-02-03⁩⁦100%⁩1.001.091 / 2
3
Phase490⁦2025-11-04⁩⁦2027-03-09⁩⁦68%⁩6.364.72—
3.1
WBS element212⁦2025-11-16⁩⁦2026-06-16⁩⁦100%⁩2.122.301 / 1
3.2
WBS element212⁦2026-03-29⁩⁦2026-10-27⁩⁦100%⁩2.122.301 / 1
3.3
WBS element490⁦2025-11-04⁩⁦2027-03-09⁩⁦5%⁩2.120.121 / 2
4
Phase105⁦2027-02-19⁩⁦2027-06-04⁩⁦0%⁩5.02——
4.1
WBS element47⁦2027-02-19⁩⁦2027-04-07⁩⁦0%⁩1.67—1 / 1
4.2
WBS element47⁦2027-03-20⁩⁦2027-05-06⁩⁦0%⁩1.67—1 / 1
4.3
WBS element47⁦2027-04-18⁩⁦2027-06-04⁩⁦0%⁩1.67—1 / 2
5
Phase76⁦2027-05-17⁩⁦2027-08-01⁩⁦0%⁩2.34——
5.1
WBS element47⁦2027-05-17⁩⁦2027-07-03⁩⁦0%⁩1.17—1 / 1
5.2
WBS element47⁦2027-06-15⁩⁦2027-08-01⁩⁦0%⁩1.17—1 / 1
Total⁦44%⁩16.737.99