Execution
Deliverable completion certificate
Evidence, inspection, acceptance and the financial link
- Form no.
- RC-PMO-F08
- Template edition
- 1.1
- Version
- V1
- Form date
- 2025-09-24
- Hijri
- 2 Rabiʻ II 1447 AH
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-020
- Project
- The Chamber’s Investment Building — Business Tower on King Fahd Road
- Portfolio
- New Headquarters & Investment Assets Portfolio
- Sector
- Investment Department
- Sponsor
- Sarah A. Al-Qarni
- Project manager
- Eng. Ahmed Y. Asiri
1The deliverableAuto-filled
- DeliverableAuto-filled
- Detailed design
- DescriptionAuto-filled
- A contractual output tied to its WBS work package.
- OwnerAuto-filled
- Hisham A. Al-Tuwairqi
- VersionAuto-filled
- V1
- Weight in the projectAuto-filled
- 6%
- DueAuto-filled
- 2025-04-10
2Evidence of completionAuto-filled
| File | Version | By | Date |
|---|---|---|---|
| PRJ-2026-020_2.1_v1.pdf | V1 | Hisham A. Al-Tuwairqi | 2025-02-23 |
3Inspection and acceptance criteria
| Criterion | Result |
|---|---|
| Matches the approved scope of work | Met |
| Quality review with no major findings | Met |
| Evidence attached and signed by the owner | Met |
| Met | 3 of 3 |
- InspectorAuto-filled
- Hisham A. Al-Tuwairqi
- Accepted byAuto-filled
- Sarah A. Al-Qarni
- Acceptance note
- Inspected and accepted against the approved acceptance criteria.
4Financial linkAuto-filled
- Contract milestoneAuto-filled
- Designs approved
- ContractAuto-filled
- CTR-2024-017
- Payment certificateAuto-filled
- Linked when the certificate is raised
- Payment against itAuto-filled
- —
Approval logChain: Deliverable acceptance & certificate · version 1
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Hisham A. Al-TuwairqiDirector, Investment | Submitted | — | 2025-02-23 14:11 |
| 2 | Evidence against the acceptance criteria | Methodology review | Ghada A. Al-ShahraniPMO — analyst | Approved | — | 2025-02-25 14:41 |
| 3 | Inspection & technical acceptance — owner | Technical acceptance | Sarah A. Al-QarniProject ownerOn behalf of Hisham A. Al-Tuwairqi | Approved | Inspected and accepted against the approved acceptance criteria. | 2025-02-26 09:48 |
| 4 | Deliverable matched to the contract line | Financial approval | Mazen A. Al-HazmiProcurement & contracts | Approved | — | 2025-02-27 11:38 |
| 5 | Certificate linked to the payment certificate | Financial approval | Munirah A. Al-KhalidiFinance | Approved | — | 2025-03-03 12:15 |
Signatures
Evidence against the acceptance criteria
Ghada A. Al-Shahrani
Approved2025-02-25
Inspection & technical acceptance — owner
Sarah A. Al-Qarni
Approved2025-02-26
Deliverable matched to the contract line
Mazen A. Al-Hazmi
Approved2025-02-27
Certificate linked to the payment certificate
Munirah A. Al-Khalidi
Approved2025-03-03