Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-022On track3PlanningStage-GateNot started

Chamber Channel & Podcast Studio — with a Media Sponsor

Add to watchlist

A filming and broadcast studio for the chamber’s channel, its podcast and the digital Tijarat Al-Riyadh magazine, co-funded by a private-sector media sponsor.

Budget (BAC)

SAR 2.3M

Actual cost

SAR 46K

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 2.3M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-03-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution7 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate7 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Chamber Channel & Podcast Studio — with a Media Sponsor

PRJ-2026-022 · Corporate Communication & Marketing · External · WP-2026-022

Not startedOn track3PlanningProject manager: Rami Al-Khatib · Sponsor: Eng. Majed S. Al-Rasheed
Progress
⁦2%⁩ / ⁦2%⁩
SPI · CPI
1.00 · 1.00
Spend
SAR 46K / SAR 2.3M
Estimate at completion
SAR 2.3M

Schedule

On plan⁦2%⁩

Planned to date ⁦2%⁩

Forecast finish: 2028-03-315 Dhuʻl-Qiʻdah 1449 AH · On time

SPI1.00Schedule performance index · 1.00CPI1.00Cost performance index · 1.00

Health dimensions

On track

Last update: 2026-10-187 Jumada I 1448 AH · Up to date

Deliverables

⁦1⁩ of ⁦1⁩ due deliverables accepted on time (⁦100%⁩)

Next milestones

  • Project plan approved2027-01-0830 Rajab 1448 AH
  • Designs approved2027-04-081 Dhuʻl-Qiʻdah 1448 AH
  • Build complete2027-08-2119 Rabiʻ I 1449 AH
  • Testing & acceptance complete2028-01-036 Shaʻban 1449 AH

Top risks

  • Privacy and copyright requirements for recorded content under the Personal Data Protection Law9

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SAR 2.3M: 1 on track and 0 red or critical. Weighted progress is 2% against 2% planned, spend SAR 0M, and EAC SAR 2.3M (SAR 0M under).

No project is more than a month behind baseline.

Riyadh Chamber of Commerce & Industry · prepared by Rami Al-Khatib in MunjazInternal

Status: On track ·Project page

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close