Project status card
28 October 2026 · 17 Jumada I 1448 AH
Chamber Channel & Podcast Studio — with a Media Sponsor
PRJ-2026-022 · Corporate Communication & Marketing · External · WP-2026-022
- Progress
- 2% / 2%
- SPI · CPI
- 1.00 · 1.00
- Spend
- SAR 46K / SAR 2.3M
- Estimate at completion
- SAR 2.3M
Schedule
Planned to date 2%
Forecast finish: 2028-03-315 Dhuʻl-Qiʻdah 1449 AH · On time
SPI1.00Schedule performance index · 1.00CPI1.00Cost performance index · 1.00Health dimensions
Last update: 2026-10-187 Jumada I 1448 AH · Up to date
Deliverables
1 of 1 due deliverables accepted on time (100%)
Next milestones
- Project plan approved2027-01-0830 Rajab 1448 AH
- Designs approved2027-04-081 Dhuʻl-Qiʻdah 1448 AH
- Build complete2027-08-2119 Rabiʻ I 1449 AH
- Testing & acceptance complete2028-01-036 Shaʻban 1449 AH
Top risks
- Privacy and copyright requirements for recorded content under the Personal Data Protection Law9
Open impediments
- None
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SAR 2.3M: 1 on track and 0 red or critical. Weighted progress is 2% against 2% planned, spend SAR 0M, and EAC SAR 2.3M (SAR 0M under).
No project is more than a month behind baseline.