PRJ-2026-025On track4ExecutionConstructionIn progress
Shaqra Branch Rehabilitation
Add to watchlistRehabilitating a leased building for the chamber’s Shaqra branch, with a service hall and a training room.
Project managerEng. Mishari K. Al-OtaibiProject sponsorEng. Sami A. Al-FraihProgrammeBuilding Rehabilitation & Efficiency Programme
Budget (BAC)
SAR 2.1M
Actual cost
SAR 741K
35% of budget
Progress
36%Awaiting acceptance 12%
Estimate at completion
SAR 2.1M
SPI · CPI
1.03Schedule performance index · 1.031.02Cost performance index · 1.02
Forecast finish
2027-09-30
On baseline
ExecutionStage 4 of 5
Next gate:Closure4 August 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started