Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-025On track4ExecutionConstructionIn progress

Shaqra Branch Rehabilitation

Add to watchlist

Rehabilitating a leased building for the chamber’s Shaqra branch, with a service hall and a training room.

Budget (BAC)

SAR 2.1M

Actual cost

SAR 741K

⁦35%⁩ of budget

Progress

⁦36%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 2.1M

SPI · CPI

1.03Schedule performance index · 1.031.02Cost performance index · 1.02

Forecast finish

⁦2027-09-30⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 August 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
RC-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2025-11-06⁩
Hijri
15 Jumada I 1447 AH
ApprovedPRJ-2026-025Shaqra Branch Rehabilitation

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-025
Project
Shaqra Branch Rehabilitation
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Member Experience & Business Development Sector
Sponsor
Eng. Sami A. Al-Fraih
Project manager
Eng. Mishari K. Al-Otaibi

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2025-10-12⁩

Baseline finish

⁦2027-09-30⁩

Forecast finish

⁦2027-09-30⁩

SPI

1.03

MilestonePlannedForecastSlip
Project plan approved⁦2026-03-09⁩⁦2026-04-07⁩+29 days
Designs approved⁦2026-07-01⁩⁦2026-08-21⁩+51 days
Build complete⁦2026-12-19⁩⁦2027-02-06⁩+49 days
Testing & acceptance complete⁦2027-06-08⁩⁦2027-06-30⁩+22 days
Final handover⁦2027-09-30⁩⁦2027-10-04⁩+4 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦4%⁩⁦2026-01-11⁩Eng. Mishari K. Al-Otaibi
Monitoring & reporting⁦3%⁩⁦2026-03-09⁩Eng. Bandar M. Al-Shammari
Detailed design⁦7%⁩⁦2026-05-05⁩Eng. Bandar M. Al-Shammari
Permits & approvals⁦7%⁩⁦2026-07-01⁩Eng. Sami A. Al-Fraih
Site works & excavation⁦15%⁩⁦2026-08-27⁩Eng. Sami A. Al-Fraih
Structure⁦12%⁩⁦2026-10-23⁩Eng. Mishari K. Al-Otaibi
Finishes⁦12%⁩⁦2026-12-19⁩Eng. Bandar M. Al-Shammari
Supply⁦9%⁩⁦2027-02-14⁩Eng. Mishari K. Al-Otaibi
Installation⁦9%⁩⁦2027-04-12⁩Eng. Bandar M. Al-Shammari
Testing & commissioning⁦9%⁩⁦2027-06-08⁩Eng. Sami A. Al-Fraih
Provisional acceptance⁦7%⁩⁦2027-08-04⁩Eng. Bandar M. Al-Shammari
Final acceptance⁦6%⁩⁦2027-09-30⁩Eng. Sami A. Al-Fraih
Accepted with a certificate⁦36%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
No risks recorded

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyEng. Mishari K. Al-Otaibi
Project ownerDeliverable status and acceptance datesFortnightlyEng. Mishari K. Al-Otaibi
PMOData and indicator updatesWeeklyEng. Mishari K. Al-Otaibi
BeneficiariesWhat changes and whenAt each milestoneEng. Mishari K. Al-Otaibi
Team memberRoleAllocation
Eng. Mishari K. Al-OtaibiProject manager⁦45%⁩
Eng. Bandar M. Al-ShammariProject owner⁦15%⁩

5QualityAuto-filled

  • Peer review of every deliverable before acceptance
  • Written acceptance criteria for every deliverable
  • A PMO audit at every gate

6BenefitsAuto-filled

BenefitBaselineTargetOwner
No benefits recorded

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Mishari K. Al-OtaibiDirector, Sustainability & Social ResponsibilitySubmitted—⁦2025-11-06⁩ 11:38
2Methodology review — PMOMethodology reviewGhada A. Al-ShahraniPMO — analystApprovedComplete against the project management plan template.⁦2025-11-10⁩ 13:10
3Technical acceptance — project ownerTechnical acceptanceEng. Bandar M. Al-ShammariProject ownerApproved—⁦2025-11-13⁩ 14:17
4Cash flow & financial commitmentFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-11-17⁩ 12:33
5Plan aligned with the contractsFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-11-18⁩ 13:10
6Sponsor approvalTechnical acceptanceEng. Sami A. Al-FraihProject sponsorApproved—⁦2025-11-23⁩ 11:38

Signatures

Methodology review — PMO

Ghada A. Al-Shahrani

Approved⁦2025-11-10⁩

Technical acceptance — project owner

Eng. Bandar M. Al-Shammari

Approved⁦2025-11-13⁩

Cash flow & financial commitment

Munirah A. Al-Khalidi

Approved⁦2025-11-17⁩

Plan aligned with the contracts

Mazen A. Al-Hazmi

Approved⁦2025-11-18⁩

Sponsor approval

Eng. Sami A. Al-Fraih

Approved⁦2025-11-23⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Eng. Mishari K. Al-Otaibi on ⁦2025-11-06⁩

  1. Methodology review

    Methodology review — PMO

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-11-10⁩ at ⁦13:10⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Eng. Bandar M. Al-Shammari · Project owner

    Approved · ⁦2025-11-13⁩ at ⁦14:17⁩

  3. Financial approval

    Cash flow & financial commitment

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-11-17⁩ at ⁦12:33⁩

  4. Financial approval

    Plan aligned with the contracts

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-11-18⁩ at ⁦13:10⁩

  5. Technical acceptance

    Sponsor approval

    Eng. Sami A. Al-Fraih · Project sponsor

    Approved · ⁦2025-11-23⁩ at ⁦11:38⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-11-06⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Eng. Mishari K. Al-Otaibi

  2. V1Returned for edit⁦2025-10-23⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Eng. Mishari K. Al-Otaibi

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close