Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-025On track4ExecutionConstructionIn progress

Shaqra Branch Rehabilitation

Add to watchlist

Rehabilitating a leased building for the chamber’s Shaqra branch, with a service hall and a training room.

Budget (BAC)

SAR 2.1M

Actual cost

SAR 741K

⁦35%⁩ of budget

Progress

⁦36%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 2.1M

SPI · CPI

1.03Schedule performance index · 1.031.02Cost performance index · 1.02

Forecast finish

⁦2027-09-30⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 August 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
RC-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-08-21⁩
Hijri
8 Rabiʻ I 1448 AH
ApprovedCRT-025-04Permits & approvals

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-025
Project
Shaqra Branch Rehabilitation
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Member Experience & Business Development Sector
Sponsor
Eng. Sami A. Al-Fraih
Project manager
Eng. Mishari K. Al-Otaibi

1The deliverableAuto-filled

DeliverableAuto-filled
Permits & approvals
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Eng. Sami A. Al-Fraih
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦7%⁩
DueAuto-filled
⁦2026-07-01⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-025_2.2_v1.pdfV1Eng. Sami A. Al-Fraih⁦2026-05-04⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Eng. Bandar M. Al-Shammari
Accepted byAuto-filled
Eng. Sami A. Al-Fraih
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Designs approved
ContractAuto-filled
CTR-2025-024
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Sami A. Al-FraihAssistant Secretary-General, Member Experience & Business DevelopmentSubmitted—⁦2026-05-04⁩ 14:23
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-05-06⁩ 10:01
3Inspection & technical acceptance — ownerTechnical acceptanceEng. Sami A. Al-FraihProject ownerOn behalf of Eng. Bandar M. Al-ShammariApprovedInspected and accepted against the approved acceptance criteria.⁦2026-05-11⁩ 11:08
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2026-05-12⁩ 09:06
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2026-05-14⁩ 10:43

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2026-05-06⁩

Inspection & technical acceptance — owner

Eng. Sami A. Al-Fraih

Approved⁦2026-05-11⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2026-05-12⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2026-05-14⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Eng. Sami A. Al-Fraih on ⁦2026-05-04⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-05-06⁩ at ⁦10:01⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Eng. Bandar M. Al-Shammari · Project owner

    Approved · ⁦2026-05-11⁩ at ⁦11:08⁩ · On behalf of Eng. Bandar M. Al-Shammari (Eng. Sami A. Al-Fraih)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-05-12⁩ at ⁦09:06⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2026-05-14⁩ at ⁦10:43⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-05-04⁩

    PRJ-2026-025_2.2_v1.pdf

    Eng. Sami A. Al-Fraih

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close