Shaqra Branch Rehabilitation Subtask Last item under this branch 2027-10-04 36% Shaqra Branch Rehabilitation Planned: 2025-10-12 → 2027-09-30 Forecast: 2025-10-12 → 2027-10-04 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-04-07 100% Management & governance Planned: 2025-10-12 → 2026-03-09 Actual: 2025-10-12 → 2026-04-07
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-01-29 100% Project plan & baseline Planned: 2025-10-12 → 2026-01-11 Actual: 2025-10-12 → 2026-01-29
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-04-07 100% Monitoring & reporting Planned: 2025-12-08 → 2026-03-09 Actual: 2025-12-19 → 2026-04-07
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-04-07 100% Project plan approved Planned: 2026-03-09 → 2026-03-09 Actual: 2026-04-07 → 2026-04-07 Project plan approved
2 Design & permits Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-08-21 100% Design & permits Planned: 2026-02-03 → 2026-07-01 Actual: 2026-02-25 → 2026-08-21
2.1 Detailed design Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-06-14 100% Detailed design Planned: 2026-02-03 → 2026-05-05 Actual: 2026-02-25 → 2026-06-14
2.2 Permits & approvals Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-08-21 100% Permits & approvals Planned: 2026-04-01 → 2026-07-01 Actual: 2026-05-04 → 2026-08-21
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-08-21 100% Designs approved Planned: 2026-07-01 → 2026-07-01 Actual: 2026-08-21 → 2026-08-21 Designs approved
3 Civil works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-02-06 47% Civil works Planned: 2026-05-28 → 2026-12-19 Forecast: 2026-07-11 → 2027-02-06 Float: 0d
3.1 Site works & excavation Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Site works & excavation Planned: 2026-05-28 → 2026-08-27 Actual: 2026-07-11 → 2026-10-26
3.2 Structure Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-20 42% Structure Planned: 2026-07-24 → 2026-10-23 Forecast: 2026-07-24 → 2026-12-20 Float: 0d Drag to change its duration +58
3.3 Finishes Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-02-06 0% Finishes Planned: 2026-09-19 → 2026-12-19 Forecast: 2026-11-22 → 2027-02-06 Float: 0d Drag to change its dates +49
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-02-06 0% Build complete Planned: 2026-12-19 → 2026-12-19 Forecast: 2027-02-06 → 2027-02-06 Float: 240d Drag to change its dates Build complete
4 MEP works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-06-30 0% MEP works Planned: 2026-11-15 → 2027-06-08 Forecast: 2027-01-09 → 2027-06-30 Float: 0d
4.1 Supply Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-03-26 0% Supply Planned: 2026-11-15 → 2027-02-14 Forecast: 2027-01-09 → 2027-03-26 Float: 0d Drag to change its dates +40
4.2 Installation Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-05-13 0% Installation Planned: 2027-01-11 → 2027-04-12 Forecast: 2027-02-26 → 2027-05-13 Float: 0d Drag to change its dates +31
4.3 Testing & commissioning Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-06-30 0% Testing & commissioning Planned: 2027-03-09 → 2027-06-08 Forecast: 2027-04-15 → 2027-06-30 Float: 0d Drag to change its dates +22
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-06-30 0% Testing & acceptance complete Planned: 2027-06-08 → 2027-06-08 Forecast: 2027-06-30 → 2027-06-30 Float: 96d Drag to change its dates Testing & acceptance complete
5 Handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-10-04 0% Handover Planned: 2027-05-05 → 2027-09-30 Forecast: 2027-06-02 → 2027-10-04 Float: 0d
5.1 Provisional acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-08-17 0% Provisional acceptance Planned: 2027-05-05 → 2027-08-04 Forecast: 2027-06-02 → 2027-08-17 Float: 0d Drag to change its dates +13
5.2 Final acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-10-04 0% Final acceptance Planned: 2027-07-01 → 2027-09-30 Forecast: 2027-07-20 → 2027-10-04 Float: 0d Drag to change its dates +4
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-10-04 0% Final handover Planned: 2027-09-30 → 2027-09-30 Forecast: 2027-10-04 → 2027-10-04 Float: 0d Drag to change its dates Final handover