Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-025On track4ExecutionConstructionIn progress

Shaqra Branch Rehabilitation

Add to watchlist

Rehabilitating a leased building for the chamber’s Shaqra branch, with a service hall and a training room.

Budget (BAC)

SAR 2.1M

Actual cost

SAR 741K

⁦35%⁩ of budget

Progress

⁦36%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 2.1M

SPI · CPI

1.03Schedule performance index · 1.031.02Cost performance index · 1.02

Forecast finish

⁦2027-09-30⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 August 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+4⁩ days vs approved

Baseline (original = approved)⁦2027-09-30⁩
Current forecast⁦2027-10-04⁩
By earned schedule⁦2028-05-28⁩
Critical activities
8
of ⁦10⁩ open activities
Late activities
7
past their baseline finish
Schedule performance
0.64
earned ÷ planned value
Next milestone
in 101 days
Build complete
Expand allCollapse all
Activity
Shaqra Branch RehabilitationPlanned: ⁦2025-10-12⁩ → ⁦2027-09-30⁩Forecast: ⁦2025-10-12⁩ → ⁦2027-10-04⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-10-12⁩ → ⁦2026-03-09⁩Actual: ⁦2025-10-12⁩ → ⁦2026-04-07⁩
Project plan & baselinePlanned: ⁦2025-10-12⁩ → ⁦2026-01-11⁩Actual: ⁦2025-10-12⁩ → ⁦2026-01-29⁩
Monitoring & reportingPlanned: ⁦2025-12-08⁩ → ⁦2026-03-09⁩Actual: ⁦2025-12-19⁩ → ⁦2026-04-07⁩
Project plan approvedPlanned: ⁦2026-03-09⁩ → ⁦2026-03-09⁩Actual: ⁦2026-04-07⁩ → ⁦2026-04-07⁩Project plan approved
Design & permitsPlanned: ⁦2026-02-03⁩ → ⁦2026-07-01⁩Actual: ⁦2026-02-25⁩ → ⁦2026-08-21⁩
Detailed designPlanned: ⁦2026-02-03⁩ → ⁦2026-05-05⁩Actual: ⁦2026-02-25⁩ → ⁦2026-06-14⁩
Permits & approvalsPlanned: ⁦2026-04-01⁩ → ⁦2026-07-01⁩Actual: ⁦2026-05-04⁩ → ⁦2026-08-21⁩
Designs approvedPlanned: ⁦2026-07-01⁩ → ⁦2026-07-01⁩Actual: ⁦2026-08-21⁩ → ⁦2026-08-21⁩Designs approved
Civil worksPlanned: ⁦2026-05-28⁩ → ⁦2026-12-19⁩Forecast: ⁦2026-07-11⁩ → ⁦2027-02-06⁩Float: ⁦0⁩d
Site works & excavationPlanned: ⁦2026-05-28⁩ → ⁦2026-08-27⁩Actual: ⁦2026-07-11⁩ → ⁦2026-10-26⁩
StructurePlanned: ⁦2026-07-24⁩ → ⁦2026-10-23⁩Forecast: ⁦2026-07-24⁩ → ⁦2026-12-20⁩Float: ⁦0⁩dDrag to change its duration+58
FinishesPlanned: ⁦2026-09-19⁩ → ⁦2026-12-19⁩Forecast: ⁦2026-11-22⁩ → ⁦2027-02-06⁩Float: ⁦0⁩dDrag to change its dates+49
Build completePlanned: ⁦2026-12-19⁩ → ⁦2026-12-19⁩Forecast: ⁦2027-02-06⁩ → ⁦2027-02-06⁩Float: ⁦240⁩dDrag to change its datesBuild complete
MEP worksPlanned: ⁦2026-11-15⁩ → ⁦2027-06-08⁩Forecast: ⁦2027-01-09⁩ → ⁦2027-06-30⁩Float: ⁦0⁩d
SupplyPlanned: ⁦2026-11-15⁩ → ⁦2027-02-14⁩Forecast: ⁦2027-01-09⁩ → ⁦2027-03-26⁩Float: ⁦0⁩dDrag to change its dates+40
InstallationPlanned: ⁦2027-01-11⁩ → ⁦2027-04-12⁩Forecast: ⁦2027-02-26⁩ → ⁦2027-05-13⁩Float: ⁦0⁩dDrag to change its dates+31
Testing & commissioningPlanned: ⁦2027-03-09⁩ → ⁦2027-06-08⁩Forecast: ⁦2027-04-15⁩ → ⁦2027-06-30⁩Float: ⁦0⁩dDrag to change its dates+22
Testing & acceptance completePlanned: ⁦2027-06-08⁩ → ⁦2027-06-08⁩Forecast: ⁦2027-06-30⁩ → ⁦2027-06-30⁩Float: ⁦96⁩dDrag to change its datesTesting & acceptance complete
HandoverPlanned: ⁦2027-05-05⁩ → ⁦2027-09-30⁩Forecast: ⁦2027-06-02⁩ → ⁦2027-10-04⁩Float: ⁦0⁩d
Provisional acceptancePlanned: ⁦2027-05-05⁩ → ⁦2027-08-04⁩Forecast: ⁦2027-06-02⁩ → ⁦2027-08-17⁩Float: ⁦0⁩dDrag to change its dates+13
Final acceptancePlanned: ⁦2027-07-01⁩ → ⁦2027-09-30⁩Forecast: ⁦2027-07-20⁩ → ⁦2027-10-04⁩Float: ⁦0⁩dDrag to change its dates+4
Final handoverPlanned: ⁦2027-09-30⁩ → ⁦2027-09-30⁩Forecast: ⁦2027-10-04⁩ → ⁦2027-10-04⁩Float: ⁦0⁩dDrag to change its datesFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦23⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦10⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦7⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Structure” needs a pace ⁦2.5⁩× faster than it has kept

It earned ⁦42%⁩ in 96 days; the forecast assumes the rest in 53 days. At the pace so far it finishes on ⁦2027-03-10⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 43 days on average — and it is getting worse

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

29
51
49
G1G2G3

The critical chain

In date order, to final acceptance

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close