Proposal
Project proposal & feasibility study
Justification, objectives, benefits, cost and initial risks
- Form no.
- RC-PMO-F01
- Template edition
- 2.1
- Version
- V1
- Form date
- 2026-07-06
- Hijri
- 21 Muharram 1448 AH
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-035
- Project
- Riyadh Economic Forum — 13th Edition
- Portfolio
- Member Services & Business Voice Portfolio
- Sector
- Business Support Sector
- Sponsor
- Eng. Ziyad A. Al-Dakheel
- Project manager
- Rami Al-Khatib
1The proposalAuto-filled
- TitleAuto-filled
- Riyadh Economic Forum — 13th Edition
- Proposed byAuto-filled
- Rami Al-Khatib
- DepartmentAuto-filled
- Riyadh Economic Forum Secretariat
- Submitted onAuto-filled
- 2026-07-06
- Proposal numberAuto-filled
- DMD-2026-035
2Justification
Preparing the five studies of the next edition, staging the forum at the Riyadh International Convention & Exhibition Center, and its partners and sponsors.
3Objectives
- Produce more influential knowledge and information
- A stronger presence in forums, events and trade delegations
Strategic objectives served
- SO-3.1 — Produce more influential knowledge and information
- SO-3.2 — A stronger presence in forums, events and trade delegations
4Expected benefits
| Kind | Benefit |
|---|---|
| No benefits recorded yet | |
5Cost & feasibility
Estimated cost
SAR 6M
Funding
The owning sector’s approved budget
| Cost line | Amount |
|---|---|
| Main contract | SAR 4.3M |
| Supervision & consulting | SAR 840K |
| Internal team | SAR 540K |
| Contingency reserve (5%) | SAR 300K |
| Total | SAR 6M |
6Initial risks
| Risk | Level | Proposed response |
|---|---|---|
| No initial risks recorded | ||
Approval logChain: Proposal & feasibility approval · version 4
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Rami Al-KhatibEvents & Riyadh Economic Forum Consultant | Submitted | — | 2026-07-06 10:43 |
| 2 | Line manager endorsement | Technical acceptance | Eng. Reem K. Al-DosariThe requester’s line manager | Approved | — | 2026-07-08 14:53 |
| 3 | PMO review | Methodology review | Ghada A. Al-ShahraniPMO — analyst | Approved | — | 2026-07-09 09:00 |
| 4 | Portfolio manager review | Technical acceptance | Approval enginePortfolio manager | Pre-breach alert | — | 2026-10-27 08:00 |
Signatures
Line manager endorsement
Eng. Reem K. Al-Dosari
Approved2026-07-08
PMO review
Ghada A. Al-Shahrani
Approved2026-07-09
Portfolio manager review
Faisal A. Al-Shehri
Awaiting decision
Cost & funding review
Munirah A. Al-Khalidi
Later
Project Approval Committee
Dr. Noura M. Al-Otaibi
Later