Preparing the five studies of the next edition, staging the forum at the Riyadh International Convention & Exhibition Center, and its partners and sponsors.
1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Forecast finish
2027-12-31
On baseline
Pre-start·Stage 1 of 5
Next gate:Initiation3 December 2026
Pre-start · Current stagePre-start · Current stage
Gate into «Initiation»DecisionNot held yetDate3 December 2026Initiation · Not startedInitiation · Not started
Gate into «Planning»DecisionNot held yetPlanning · Not startedPlanning · Not started
Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Project plan & baselinePlanned: 2027-02-01 → 2027-03-19Forecast: 2027-02-01 → 2027-04-04Float: 0dDrag to change its dates+16
2027-05-130%
Monitoring & reportingPlanned: 2027-03-02 → 2027-04-17Forecast: 2027-03-12 → 2027-05-13Float: 0dDrag to change its dates+26
2027-05-130%
Project plan approvedPlanned: 2027-04-17 → 2027-04-17Forecast: 2027-05-13 → 2027-05-13Float: 351dDrag to change its datesProject plan approved