RSK-0021 Material
Main contractor cash-flow distress and unpaid subcontractors
Converting the Current Headquarters into a Member Services Centre & Committee Rooms Financial 25 Critical SAR 1.8M Eng. Waleed O. Al-Juhani Eng. Waleed O. Al-Juhani Director, Facilities Operations & Maintenance P-021 · w.aljuhani@chamber.sa Escalate Escalated In 8 days 2026-11-05 · 25 Jumada I 1448 AH 1 d RSK-0015 Material
Steel and concrete price rises driving price-adjustment claims
The Chamber’s New Headquarters Building Financial 20 Critical SAR 2.4M Eng. Ahmed Y. Asiri Eng. Ahmed Y. Asiri Director, Construction Projects & Buildings P-020 · a.asiri@chamber.sa Escalate Escalated In 18 days 2026-11-15 · 5 Jumada II 1448 AH 4 d RSK-0016 Material
Late handover of the northern plot and utility diversions in zones 3 and 4
The Chamber’s New Headquarters Building Schedule 20 Critical SAR 1.6M Eng. Bandar M. Al-Shammari Eng. Bandar M. Al-Shammari Director General, Facilities & General Services P-013 · b.alshammari@chamber.sa Escalate Escalated In 64 days 2026-12-31 · 22 Rajab 1448 AH 4 d RSK-0026 Material
Contractor financial claims piling up over unapproved variations
Training & Employment Centre Complex Financial 20 Critical SAR 2.1M Eng. Shahad M. Al-Malki Eng. Shahad M. Al-Malki Senior Project Manager — Buildings & Facilities P-022 · s.almalki@chamber.sa Escalate Escalated In 13 days 2026-11-10 · 30 Jumada I 1448 AH 3 d RSK-0034 Material
Unforeseen ground conditions and groundwater at the foundations of axes 12 to 16
The Chamber’s Investment Building — Business Tower on King Fahd Road Technical 20 Critical SAR 1.4M Eng. Ahmed Y. Asiri Eng. Ahmed Y. Asiri Director, Construction Projects & Buildings P-020 · a.asiri@chamber.sa Escalate Escalated In 23 days 2026-11-20 · 10 Jumada II 1448 AH 5 d RSK-0044 Material
Late land allocation and title deed from the owning entity in Wadi Al-Dawasir
Wadi Al-Dawasir Branch Building Regulatory 20 Critical SAR 600K Eng. Shahad M. Al-Malki Eng. Shahad M. Al-Malki Senior Project Manager — Buildings & Facilities P-022 · s.almalki@chamber.sa Escalate Escalated In 64 days 2026-12-31 · 22 Rajab 1448 AH 22 d RSK-0001 Material
Nafath and Government Service Bus integration interfaces not ready on time
My Business Portal 2.0 — the Unified Member Journey Technical 16 High SAR 120K Eng. Sultan F. Al-Ghamdi Eng. Sultan F. Al-Ghamdi Project Manager, My Business Portal 2.0 P-005 · s.alghamdi@chamber.sa Mitigate Open In 18 days 2026-11-15 · 5 Jumada II 1448 AH 2 d RSK-0002 Material
Shortage of integration and back-end engineers on the vendor team
My Business Portal 2.0 — the Unified Member Journey Resource 16 High SAR 92.5K Eng. Sultan F. Al-Ghamdi Eng. Sultan F. Al-Ghamdi Project Manager, My Business Portal 2.0 P-005 · s.alghamdi@chamber.sa Escalate Escalated In 8 days 2026-11-05 · 25 Jumada I 1448 AH 2 d RSK-0012 Material
Customisation and My Business portal integration costs exceeding the approved contingency
Chamber ERP on Dynamics 365 Financial 16 High SAR 340K Dana S. Al-Saleh Dana S. Al-Saleh Director, Enterprise Systems & Integration P-025 · d.alsaleh@chamber.sa Escalate Escalated In 13 days 2026-11-10 · 30 Jumada I 1448 AH 5 d RSK-0017 Material
Contractor claim for a 120-day extension with compensation
The Chamber’s New Headquarters Building Contractual 16 High SAR 925K Khalid N. Al-Mutairi Khalid N. Al-Mutairi Senior Finance & Procurement Specialist P-007 · k.almutairi@chamber.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 8 d RSK-0019 Material
Exchange-rate swings on imported equipment without fixed prices
Disaster Recovery Centre for the Chamber’s Systems Financial 16 High SAR 370K Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@chamber.sa Mitigate Open In 23 days 2026-11-20 · 10 Jumada II 1448 AH 7 d RSK-0024 Material
Ground-improvement costs up after the geotechnical survey
Chamber Branch & Manufacturers’ Service Centre — Second Industrial City Financial 16 High SAR 1.1M Eng. Fahad T. Al-Sulami Eng. Fahad T. Al-Sulami Senior Project Manager — Branches & Service Centres P-023 · f.alsulami@chamber.sa Escalate Escalated In 15 days 2026-11-12 · 2 Jumada II 1448 AH 6 d RSK-0027 Material
Late delivery of curtain-wall glazing from the overseas factory
Training & Employment Centre Complex Schedule 16 High SAR 750K Eng. Shahad M. Al-Malki Eng. Shahad M. Al-Malki Senior Project Manager — Buildings & Facilities P-022 · s.almalki@chamber.sa Mitigate Open In 48 days 2026-12-15 · 6 Rajab 1448 AH 3 d RSK-0036 Material
Municipality late bringing utilities and access roads to the site
Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality Financial 16 High SAR 700K Yousef A. Al-Omari Yousef A. Al-Omari Executive Director, Events & Trade Delegations P-016 · y.alomari@chamber.sa Mitigate Open In 64 days 2026-12-31 · 22 Rajab 1448 AH 56 d RSK-0043 Material
Funding left out of the 2027 budget, keeping the tender suspended
Energy Retrofit of the Chamber’s Existing Buildings (ESCO) Financial 16 High SAR 240K Eng. Mishari K. Al-Otaibi Eng. Mishari K. Al-Otaibi Director, Sustainability & Social Responsibility P-028 · m.alotaibi@chamber.sa Escalate Escalated In 48 days 2026-12-15 · 6 Rajab 1448 AH 20 d RSK-0022 Material
Fire-fighting and evacuation systems failing Civil Defence requirements
Converting the Current Headquarters into a Member Services Centre & Committee Rooms Regulatory 15 High SAR 600K Eng. Mishari K. Al-Otaibi Eng. Mishari K. Al-Otaibi Director, Sustainability & Social Responsibility P-028 · m.alotaibi@chamber.sa Mitigate Open In 79 days 2027-01-15 · 7 Shaʻban 1448 AH 9 d RSK-0028 Material
Possible removal of the MEP subcontractor
Training & Employment Centre Complex Contractual 15 High SAR 475K Eng. Abdulrahman S. Al-Harbi Eng. Abdulrahman S. Al-Harbi Director General, Training & Entrepreneurship P-014 · ab.alharbi@chamber.sa Mitigate Open In 28 days 2026-11-25 · 15 Jumada II 1448 AH 10 d RSK-0046 Material
Tender prices 18% above the engineer’s estimate
Chamber Conference & Exhibition Hall — Phase 1 Financial 15 High SAR 4.7M Eng. Ibrahim A. Al-Ghamdi Eng. Ibrahim A. Al-Ghamdi Director, Engineering Supervision of Construction Projects P-036 · i.alghamdi@chamber.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 5 d RSK-0003
Late sign-off of membership and attestation requirements by the owning departments
My Business Portal 2.0 — the Unified Member Journey Stakeholder 12 Medium SAR 60K Eng. Reem K. Al-Dosari Eng. Reem K. Al-Dosari Head of the My Business Portal & Programme Manager, Digital Member Journey P-004 · r.aldosari@chamber.sa Mitigate Open In 23 days 2026-11-20 · 10 Jumada II 1448 AH 6 d RSK-0006
Possible critical findings in the pre-launch penetration test
My Business Portal 2.0 — the Unified Member Journey Security 12 Medium SAR 30K Eng. Yasser M. Al-Zahrani Eng. Yasser M. Al-Zahrani Director, Cybersecurity P-026 · y.alzahrani@chamber.sa Mitigate Open In 74 days 2027-01-10 · 2 Shaʻban 1448 AH 8 d RSK-0013
Late migration and reconciliation of historical financial data
Chamber ERP on Dynamics 365 Schedule 12 Medium SAR 105K Dana S. Al-Saleh Dana S. Al-Saleh Director, Enterprise Systems & Integration P-025 · d.alsaleh@chamber.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 5 d RSK-0020
Late delivery of cooling units and standby generators
Disaster Recovery Centre for the Chamber’s Systems Schedule 12 Medium SAR 160K Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@chamber.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 7 d RSK-0023
Central HVAC failures during commissioning
Converting the Current Headquarters into a Member Services Centre & Committee Rooms Technical 12 Medium SAR 280K Eng. Waleed O. Al-Juhani Eng. Waleed O. Al-Juhani Director, Facilities Operations & Maintenance P-021 · w.aljuhani@chamber.sa Mitigate Open In 53 days 2026-12-20 · 11 Rajab 1448 AH 9 d RSK-0025
Late building permits from the Riyadh Region Municipality
Chamber Branch & Manufacturers’ Service Centre — Second Industrial City Regulatory 12 Medium SAR 300K Eng. Fahad T. Al-Sulami Eng. Fahad T. Al-Sulami Senior Project Manager — Branches & Service Centres P-023 · f.alsulami@chamber.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 6 d RSK-0031
Late integration of the central monitoring room with building systems
Smart Access, Visitor & Event Management at HQ & the Branches Technical 12 Medium SAR 70K Eng. Waleed O. Al-Juhani Eng. Waleed O. Al-Juhani Director, Facilities Operations & Maintenance P-021 · w.aljuhani@chamber.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 44 d RSK-0033
Municipal objections to trenching in built-up districts
Unified Enterprise Network for HQ & the Branches Stakeholder 12 Medium SAR 110K Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@chamber.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 37 d RSK-0035
Pile lengths exceeding contract quantities
The Chamber’s Investment Building — Business Tower on King Fahd Road Cost 12 Medium SAR 420K Eng. Ahmed Y. Asiri Eng. Ahmed Y. Asiri Director, Construction Projects & Buildings P-020 · a.asiri@chamber.sa Mitigate Open In 48 days 2026-12-15 · 6 Rajab 1448 AH 5 d RSK-0018
Safety incidents around cranes and deep excavations
The Chamber’s New Headquarters Building Technical 10 Medium SAR 200K Eng. Ahmed Y. Asiri Eng. Ahmed Y. Asiri Director, Construction Projects & Buildings P-020 · a.asiri@chamber.sa Mitigate In progress In 245 days 2027-06-30 · 25 Muharram 1449 AH 14 d RSK-0042
Undetected vulnerabilities in legacy systems before SOC onboarding
Chamber Cybersecurity Programme Security 10 Medium SAR 150K Eng. Yasser M. Al-Zahrani Eng. Yasser M. Al-Zahrani Director, Cybersecurity P-026 · y.alzahrani@chamber.sa Mitigate In progress In 34 days 2026-12-01 · 21 Jumada II 1448 AH 2 d RSK-0005
Incomplete migration of membership and open-request data from the current My Business portal
My Business Portal 2.0 — the Unified Member Journey Technical 9 Medium SAR 37.5K Rakan F. Al-Mohammadi Rakan F. Al-Mohammadi Data Engineer P-032 · r.almohammadi@chamber.sa Mitigate Open In 34 days 2026-12-01 · 21 Jumada II 1448 AH 7 d RSK-0007
Membership and branch staff resisting the new digital procedures
My Business Portal 2.0 — the Unified Member Journey Stakeholder 9 Medium SAR 15K Nouf M. Al-Balawi Nouf M. Al-Balawi Change Management Specialist P-035 · n.albalawi@chamber.sa Mitigate In progress In 110 days 2027-02-15 · 8 Ramadan 1448 AH 13 d RSK-0010
Mobile-app team competing with the platform for the same people
My Business Portal 2.0 — the Unified Member Journey Resource 9 Medium SAR 26K Eng. Reem K. Al-Dosari Eng. Reem K. Al-Dosari Head of the My Business Portal & Programme Manager, Digital Member Journey P-004 · r.aldosari@chamber.sa Mitigate Open In 21 days 2026-11-18 · 8 Jumada II 1448 AH 3 d RSK-0048
Cloud hosting contract signed late
My Business Portal 2.0 — the Unified Member Journey Contractual 9 Medium — Khalid N. Al-Mutairi Khalid N. Al-Mutairi Senior Finance & Procurement Specialist P-007 · k.almutairi@chamber.sa Accept Closed 2025-07-01 2025-07-01 · 6 Muharram 1447 AH 479 d RSK-0014
Implementation consultants’ contracts ending before go-live
Chamber ERP on Dynamics 365 Resource 9 Medium SAR 45K Munirah A. Al-Khalidi Munirah A. Al-Khalidi Director General, Finance & Procurement P-018 · m.alkhalidi@chamber.sa Mitigate Open In 48 days 2026-12-15 · 6 Rajab 1448 AH 12 d RSK-0029
Cloud consumption costs above estimate
Moving the Chamber’s Systems & Website to the Cloud Financial 9 Medium SAR 130K Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@chamber.sa Mitigate Open In 64 days 2026-12-31 · 22 Rajab 1448 AH 11 d RSK-0030
Camera and gate quantity variances between drawings and site
Smart Access, Visitor & Event Management at HQ & the Branches Financial 9 Medium SAR 90K Eng. Waleed O. Al-Juhani Eng. Waleed O. Al-Juhani Director, Facilities Operations & Maintenance P-021 · w.aljuhani@chamber.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 44 d RSK-0032
Higher reinstatement costs after network trenching
Unified Enterprise Network for HQ & the Branches Financial 9 Medium SAR 195K Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@chamber.sa Mitigate Open In 64 days 2026-12-31 · 22 Rajab 1448 AH 37 d RSK-0037
Too few accredited data owners in the sectors and departments
Business Observatory & Data Governance Resource 9 Medium SAR 32.5K Rahaf I. Al-Nefaie Rahaf I. Al-Nefaie Director, Data & AI P-027 · r.alnefaie@chamber.sa Mitigate Open In 34 days 2026-12-01 · 21 Jumada II 1448 AH 8 d RSK-0038
High UAT defect count in the outgoing-mail module
Correspondence & Document Management System Technical 9 Medium SAR 24K Dana S. Al-Saleh Dana S. Al-Saleh Director, Enterprise Systems & Integration P-025 · d.alsaleh@chamber.sa Mitigate Open In 13 days 2026-11-10 · 30 Jumada I 1448 AH 7 d RSK-0039
Late supply of audio-visual systems for the Premium Members Centre rooms
New Premium Members Centre & VIP Lounges Schedule 9 Medium SAR 105K Eng. Fahad T. Al-Sulami Eng. Fahad T. Al-Sulami Senior Project Manager — Branches & Service Centres P-023 · f.alsulami@chamber.sa Mitigate Open In 64 days 2026-12-31 · 22 Rajab 1448 AH 4 d RSK-0040
Low uptake of the Fast Track readiness assessment among start-ups
Entrepreneurship Fast Track Platform Stakeholder 9 Medium SAR 12.5K Ghada A. Al-Shahrani Ghada A. Al-Shahrani Director, Entrepreneurship & Young Businesspeople P-029 · g.alshahrani@chamber.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 34 d RSK-0047
Privacy and copyright requirements for recorded content under the Personal Data Protection Law
Chamber Channel & Podcast Studio — with a Media Sponsor Regulatory 9 Medium SAR 45K Eng. Yasser M. Al-Zahrani Eng. Yasser M. Al-Zahrani Director, Cybersecurity P-026 · y.alzahrani@chamber.sa Mitigate Open In 95 days 2027-01-31 · 23 Shaʻban 1448 AH 10 d RSK-0004
Cloud hosting capacity exceeded at launch
My Business Portal 2.0 — the Unified Member Journey Technical 8 Medium SAR 45K Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@chamber.sa Mitigate In progress In 48 days 2026-12-15 · 6 Rajab 1448 AH 9 d RSK-0008
Late delivery of identity & access management licences
My Business Portal 2.0 — the Unified Member Journey Contractual 6 Low SAR 22.5K Khalid N. Al-Mutairi Khalid N. Al-Mutairi Senior Finance & Procurement Specialist P-007 · k.almutairi@chamber.sa Transfer Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 10 d RSK-0011
Updated user-experience standards from the Digital Government Authority
My Business Portal 2.0 — the Unified Member Journey Regulatory 6 Low SAR 14K Lama S. Al-Harbi Lama S. Al-Harbi Senior Business Analyst — Member Services P-006 · l.alharbi@chamber.sa Accept Open In 95 days 2027-01-31 · 23 Shaʻban 1448 AH 16 d RSK-0045
Preliminary-handover snags on the fire and alarm systems
Business Centre (Exit 6) Branch Rehabilitation Technical 6 Low SAR 30K Eng. Waleed O. Al-Juhani Eng. Waleed O. Al-Juhani Director, Facilities Operations & Maintenance P-021 · w.aljuhani@chamber.sa Mitigate Open In 15 days 2026-11-12 · 2 Jumada II 1448 AH 2 d