SO-4.2 · Streamlined governance and dependable technology

Performance measurement & governance

On trackDelivered wholly through projectsImproving the Organisation

The institutional performance system and Power BI dashboards, the operational plans and scorecards for the 2025–2030 strategy, and the enterprise risk & continuity framework.

⁦78%⁩

Initiative weighted progress

⁦77.7%⁩

Σ each project’s contribution × its actual progress, over the shares that count

Linked projects’ progress

⁦77.7%⁩

Σ contribution × progress, projects only

Contributions assigned

⁦90%⁩

⁦10⁩ points short of 100%

Primary projects’ budget

830K

3 primary projects

Linked projects and their contributions

Strategy management approves each share; every change is kept in the initiative’s history

ProjectLinkContributionActual progressContribution × progress
Institutional Performance Measurement & Power BI Dashboards

PRJ-2026-012

Primary⁦40%⁩⁦76%⁩⁦30.4%⁩
Operational Plans & Scorecards for the 2025–2030 Strategy

PRJ-2026-028

Primary⁦35%⁩⁦70%⁩⁦24.5%⁩
Enterprise Risk & Business Continuity Framework

PRJ-2026-030

Primary⁦15%⁩⁦100%⁩⁦15.0%⁩

Linked projects’ progress

Σ (contribution × progress) = ⁦69.9%⁩ points ÷ shares counted ⁦90%⁩ = ⁦77.7%⁩

Initiative progress

The initiative runs wholly through its projects, so its progress is theirs: ⁦77.7%⁩

Shares add up to ⁦90%⁩, not 100%.

Scope, outputs & phases

As approved with the initiative: what is in scope, what it delivers, and its delivery phases on the timeline.

Scope

Institutional performance measurement and Power BI dashboards, operational plans and scorecards, and risk & continuity management.

Outputs

  • Institutional performance dashboards on Power BI
  • An operational plan per department
  • The risk & continuity framework

Delivery phases

  • Risk & continuity

    2025-03-09 — 2026-08-31

  • Performance measurement

    2025-09-07 — 2026-12-24

  • Operational plans

    2026-05-03 — 2026-12-15

Today · ⁦2026-10-28⁩

Impact KPIs & benefits

Measured apart from delivery progress: an initiative can be well advanced with no impact yet, and the other way round

Impact KPIs

The strategic KPIs the initiative moves

Benefits

Benefits registered for its projects, planned vs realised

These KPIs and benefits do not enter the weighted progress above, and progress does not enter them.

Three separate measures

An example from this initiative: Institutional Performance Measurement & Power BI Dashboards

1Deliverable weight in the project

⁦30.0%⁩

Weight of «Design» among its deliverables

Deliverable weights add up to 100% inside the project; it progresses as they are accepted.

See where it comes from

2Project weight in the portfolio

⁦18.3%⁩

Its relative weight in Institutional Excellence & Capability Portfolio

Set by the project weight model; it feeds portfolio progress: relative weight × actual progress.

See where it comes from

3Contribution to the initiative

⁦40%⁩

Its contribution to «Performance measurement & governance»

Approved by strategy management; it feeds this initiative’s progress only.

Each is set in its own place and moves neither of the others: changing a deliverable’s weight touches neither the project’s portfolio weight nor its contribution.

Risks, obstacles & deviations

The initiative’s own risks and obstacles, the highest open risks of its projects, and the budget and schedule deviation.

  • Possible riskMediumOpen

    Departments late entering KPI readings weaken the dashboards

    Response: Automatic reminders and escalation after seven days

    Tariq S. Al-YamiTariq S. Al-YamiHead, Institutional Performance & QualityP-040t.alyami@chamber.sa

Highest risks of the linked projectsRisk register

No high open risks on its projects.

Deviation

Budget: projects total SAR 830K against the estimate SAR 900K

Schedule: last project ends ⁦2026-12-24⁩ against the initiative end ⁦2026-12-31⁩

Approval & change log

This item’s definition as approved in the plan version in force, and every change request on it with the old and proposed values and the decision.

Approved in plan version ⁦1.1⁩Board resolution BRD-1447-092026-03-256 Shawwal 1447 AH

No change requests on this item since the plan was approved.