Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-030On track5ClosureWaterfallIn progress

Enterprise Risk & Business Continuity Framework

Add to watchlist

A risk framework, register and appetite approved by the board, in line with ISO requirements.

Project managerTariq S. Al-YamiProject sponsorDr. Mohammed I. Al-Subaie

Budget (BAC)

SAR 180K

Actual cost

SAR 173K

⁦96%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 173K

SPI · CPI

1.00Schedule performance index · 1.001.04Cost performance index · 1.04

Forecast finish

⁦2026-08-31⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate3 June 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate19 July 2026Closure · Current stageClosure · Current stage

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+6

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦100% done against 100% planned⁩.

⁦SPI 1⁩.⁦00⁩, ⁦CPI 1⁩.⁦04⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Improving the OrganisationSO-4.2Streamlined governance and dependable technology

Main initiative

SI-4.2.2Performance measurement & governance

Contribution to the initiative⁦22%⁩

The project’s share of the initiative’s project budget (3 projects)

Secondary links

No secondary links

Annual work-plan line
Added outside the annual work plan
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦100%⁩

Awaiting acceptance ⁦0%⁩

Not handed in ⁦0%⁩

10 deliverables accepted

  • Target model⁦15%⁩
  • Roadmap⁦15%⁩
  • Wave 1⁦15%⁩
  • Wave 2⁦15%⁩
  • Current-state assessment⁦10%⁩
  • Benchmarking⁦10%⁩
  • Project plan & baseline⁦5%⁩
  • Monitoring & reporting⁦5%⁩

0 deliverables under inspection or acceptance

    Progress & earned value

    ⁦5⁩ of ⁦5⁩ milestones complete

    Earned-value curve

    Planned, earned and actual to the data date, cumulative, with the forecast cost tail

    • Planned value
    • Earned value
    • Actual cost
    • Estimate at completion
    • Budget at completion

    Budget & commitments

    Commitments are ⁦97%⁩ of budget

    173K/ 180K7,000projected saving(⁦3.9%⁩)
    Actual spend
    173K
    Committed
    175K
    Approved budget
    180K
    Estimate at completion
    173K

    Next milestones

    • Every milestone is complete

    Waiting on someone

    ⁦0⁩ approvals and ⁦0⁩ open actions on this project

    Approvals & requests

    From «My actions» for this project

    • No approvals pending

    Actions

    ⁦0⁩ open

    • Capture lessons learned for the risk & continuity frameworkTariq S. Al-Yami⁦2026-10-20⁩2026-10-209 Jumada I 1448 AHLow

    Change requests

    Cost and schedule impact

    • No change requests

    Risks & impediments

    0 open risks, exposure SAR 0

    Risk map

    Probability
    5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
    4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
    3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
    2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
    1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
    12345

    Impact

    • Critical0
    • High0
    • Medium0
    • Low0

    Top risks

    • No open risks

    Open impediments

    ⁦0⁩ escalated

    • No open impediments

    Deliverables

    ⁦10⁩ of ⁦10⁩ approved

    • Project plan & baseline030-D1 · V1 · CRT-030-01⁦5%⁩Tariq S. Al-Yami⁦2025-05-30⁩2025-05-303 Dhuʻl-Hijjah 1446 AHApproved
    • Monitoring & reporting030-D2 · V1 · CRT-030-02⁦5%⁩Dr. Amal F. Al-Sudairi⁦2025-07-19⁩2025-07-1924 Muharram 1447 AHApproved
    • Current-state assessment030-D3 · V1 · CRT-030-03⁦10%⁩Dr. Amal F. Al-Sudairi⁦2025-09-08⁩2025-09-0816 Rabiʻ I 1447 AHApproved
    • Benchmarking030-D4 · V1 · CRT-030-04⁦10%⁩Dr. Mohammed I. Al-Subaie⁦2025-10-29⁩2025-10-297 Jumada I 1447 AHApproved
    • Target model030-D5 · V1 · CRT-030-05⁦15%⁩Dr. Mohammed I. Al-Subaie⁦2025-12-19⁩2025-12-1928 Jumada II 1447 AHApproved
    • Roadmap030-D6 · V1 · CRT-030-06⁦15%⁩Tariq S. Al-Yami⁦2026-02-08⁩2026-02-0820 Shaʻban 1447 AHApproved
    • Wave 1030-D7 · V1 · CRT-030-07⁦15%⁩Tariq S. Al-Yami⁦2026-03-31⁩2026-03-3112 Shawwal 1447 AHApproved
    • Wave 2030-D8 · V1 · CRT-030-08⁦15%⁩Dr. Amal F. Al-Sudairi⁦2026-05-21⁩2026-05-214 Dhuʻl-Hijjah 1447 AHApproved
    • Knowledge transfer030-D9 · V1 · CRT-030-09⁦5%⁩Dr. Amal F. Al-Sudairi⁦2026-07-11⁩2026-07-1126 Muharram 1448 AHApproved
    • Final report030-D10 · V1 · CRT-030-10⁦5%⁩Dr. Mohammed I. Al-Subaie⁦2026-08-31⁩2026-08-3118 Rabiʻ I 1448 AHApproved

    Team, contracts & documents

    Team

    2 members

    Tariq S. Al-Yami · Head, Institutional Performance & QualityDr. Noura M. Al-Otaibi · Director, Project Management Office
    • Tariq S. Al-YamiTariq S. Al-YamiHead, Institutional Performance & QualityProject manager (closure)P-040t.alyami@chamber.sa⁦20%⁩
    • Dr. Noura M. Al-OtaibiDr. Noura M. Al-OtaibiDirector, Project Management OfficeClosure assurance & lessons learnedP-002n.alotaibi@chamber.sa⁦15%⁩

    Contracts

    0 contracts

    • No external contracts — delivered in-house
    Esc

    Quick actions

    Go to

    Projects

    ↑↓to move↵to openEscto close