PRJ-2026-030On track5ClosureWaterfallIn progress

Enterprise Risk & Business Continuity Framework

Add to watchlist

A risk framework, register and appetite approved by the board, in line with ISO requirements.

Project managerTariq S. Al-YamiProject sponsorDr. Mohammed I. Al-Subaie

Budget (BAC)

SAR 180K

Actual cost

SAR 173K

⁦96%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 173K

SPI · CPI

1.00Schedule performance index · 1.001.04Cost performance index · 1.04

Forecast finish

⁦2026-08-31⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate3 June 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate19 July 2026Closure · Current stageClosure · Current stage

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 180K split into spent, committed and left, with the estimate at completion

EAC SAR 173K
Revised request SAR 180K
  • Actual spendSAR 173K
  • Committed, not spentSAR 2,000
  • Allotted, uncommittedSAR 0
  • Contingency availableSAR 5,400

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 165K
Original budgetwhen the first baseline was approved
SAR 180K
Approved budgetafter approved change requests
SAR 180K
Current budgetavailable to spend now
SAR 180K
Revised budgetif the pending changes are approved
SAR 180K

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 175K
Contracts0 active contracts
SAR 0
Purchase orders⁦2⁩ orders
SAR 175K
Remaining budgetapproved less actual
SAR 7,000

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 173K
Accrualswork done, not yet invoiced
SAR 7,000
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 173K
ContingencySAR 3,600 drawn of SAR 9,000
SAR 5,400

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 165K
ApprovedSAR 180K
Estimate at completionSAR 173K
Approved is SAR 15K (⁦9.1%⁩) above the estimate
The estimate at completion is SAR 8,000 (⁦4.8%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2024-12-24⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-21030
  • WBS elements⁦5⁩ elements · P-2026-030.01 …
  • Purchase orders⁦2⁩ synced · ⁦0⁩ manual
  • Invoices & certificatesNo certificates
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 3,600 drawn of SAR 9,000

  • Covering realised delivery risks⁦2026-08-29⁩SAR 3,600

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance0.020.020.020.02⁦+0.00⁩
2Diagnosis0.030.030.030.03⁦+0.00⁩
3Design0.050.050.050.05⁦+0.00⁩
4Implementation0.050.050.050.05⁦+0.00⁩
5Handover & knowledge transfer0.020.020.020.02⁦+0.00⁩
Unallocated contingency0.010.000.000.00⁦+0.00⁩
Total0.180.180.170.17⁦+0.01⁩

Budget split

WBS

SAR 180K

Budget

  • Management & governanceSAR 17.5K⁦10%⁩
  • DiagnosisSAR 34.9K⁦19%⁩
  • DesignSAR 52.4K⁦29%⁩
  • ImplementationSAR 52.4K⁦29%⁩
  • Handover & knowledge transferSAR 17.5K⁦10%⁩
  • Unallocated contingencySAR 5,400⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

No data to show yet

It appears here once the first value is recorded.

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2026-08-31⁩

SPI(t) ⁦1.00⁩ against the approved finish ⁦2026-08-31⁩

Planned valuePV
SAR 180K
The value of the work that should be done by today.
PV
Earned valueEV
SAR 180K
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 173K
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 180K
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.01⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦+0.00⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.04
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
1.00
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 173K
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 0
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.01⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
0.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 173K
  • If the rest goes to planSAR 173K
  • At cost and schedule performanceSAR 173K
  • The PM’s bottom-up estimateSAR 173K
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 173K

Variance at completion: ⁦+0.01⁩ SAR M