Did it reach its goal?
Yes100%
Every deliverable done; the board approved the risk appetite.
A risk framework, register and appetite approved by the board, in line with ISO requirements.
Budget (BAC)
Actual cost
96% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ClosureStage 5 of 5
Closing
Finish the open items and hand the benefits to their owner, then close the project. No project closes without lessons learned.
Seven mandatory items before any project closes.
Deliverables acceptedDone
Framework, policies and risk appetite approved by the chamber’s board
Dr. Amal F. Al-SudairiDone 2026-08-31
Financial closureIn progress
Reconciling SAR 173K spend; closing the last SAR 2K of commitments
Haifa S. Al-RuwailiPlanned 2026-11-05
Contract closureDone
No external contracts — delivered in-house
Tariq S. Al-YamiDone 2026-09-10
Documents archivedIn progress
31 of 38 documents archived
Tariq S. Al-YamiPlanned 2026-11-02Evidence
Lessons learnedDone
One lesson published on sector risk champions
Tariq S. Al-YamiDone 2026-10-14Evidence
Benefits owner assignedNot started
Hand the response-plan benefit from the PM to the Director General, Strategy & the PMO
Dr. Amal F. Al-SudairiPlanned 2026-10-31
Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?
Did it reach its goal?
Yes100%
Every deliverable done; the board approved the risk appetite.
Did it stay on budget?
Yes−3.9%
SAR 173K against 180K, on time.
Were the benefits realised?
Partly78%
78% of risks have a response plan vs 90% targeted at 12 months.
What did we learn?
Yes1
One lesson published; a second proposed on linking the register to Munjaz.
What should improve?
Partly—
To complete in the post-closure review session.
1 lesson — offered automatically to similar projects when they are created.
Each benefit moves from the project manager to an owner who measures it after closure.
baseline 35 · now 78 · target 90 %