PRJ-2026-030On track5ClosureWaterfallIn progress

Enterprise Risk & Business Continuity Framework

Add to watchlist

A risk framework, register and appetite approved by the board, in line with ISO requirements.

Project managerTariq S. Al-YamiProject sponsorDr. Mohammed I. Al-Subaie

Budget (BAC)

SAR 180K

Actual cost

SAR 173K

⁦96%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 173K

SPI · CPI

1.00Schedule performance index · 1.001.04Cost performance index · 1.04

Forecast finish

⁦2026-08-31⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate3 June 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate19 July 2026Closure · Current stageClosure · Current stage

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work174.6K⁦15⁩ elements
Unallocated contingency5,400SAR 9,000
Budget at completion180KPRJ-2026-030
Weighted progress⁦100%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project596⁦2025-03-09⁩⁦2026-10-26⁩⁦100%⁩0.170.17—
1
Phase147⁦2025-03-09⁩⁦2025-08-03⁩⁦100%⁩0.020.02—
1.1
WBS element90⁦2025-03-09⁩⁦2025-06-07⁩⁦100%⁩0.010.010 / 1
1.2
WBS element91⁦2025-05-04⁩⁦2025-08-03⁩⁦100%⁩0.010.011 / 2
2
Phase147⁦2025-06-30⁩⁦2025-11-24⁩⁦100%⁩0.030.03—
2.1
WBS element90⁦2025-06-30⁩⁦2025-09-28⁩⁦100%⁩0.020.021 / 1
2.2
WBS element91⁦2025-08-25⁩⁦2025-11-24⁩⁦100%⁩0.020.021 / 2
3
Phase146⁦2025-10-21⁩⁦2026-03-16⁩⁦100%⁩0.050.05—
3.1
WBS element90⁦2025-10-21⁩⁦2026-01-19⁩⁦100%⁩0.030.031 / 1
3.2
WBS element90⁦2025-12-16⁩⁦2026-03-16⁩⁦100%⁩0.030.031 / 2
4
Phase147⁦2026-02-10⁩⁦2026-07-07⁩⁦100%⁩0.050.05—
4.1
WBS element91⁦2026-02-10⁩⁦2026-05-12⁩⁦100%⁩0.030.031 / 1
4.2
WBS element90⁦2026-04-08⁩⁦2026-07-07⁩⁦100%⁩0.030.031 / 2
5
Phase145⁦2026-06-03⁩⁦2026-10-26⁩⁦100%⁩0.020.02—
5.1
WBS element91⁦2026-06-03⁩⁦2026-09-02⁩⁦100%⁩0.010.011 / 1
5.2
WBS element88⁦2026-07-30⁩⁦2026-10-26⁩⁦100%⁩0.010.011 / 1
Total⁦100%⁩0.170.17