Enterprise Risk & Business Continuity Framework
Add to watchlistA risk framework, register and appetite approved by the board, in line with ISO requirements.
Budget (BAC)
Actual cost
96% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate3 June 2025Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate19 July 2026Closure · Current stageClosure · Current stage
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-07-19 | 2025-08-03 | +15 days | Tariq S. Al-YamiTariq S. Al-YamiHead, Institutional Performance & QualityP-040t.alyami@chamber.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-10-29 | 2025-11-24 | +26 days | Tariq S. Al-YamiTariq S. Al-YamiHead, Institutional Performance & QualityP-040t.alyami@chamber.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-02-08 | 2026-03-16 | +36 days | Tariq S. Al-YamiTariq S. Al-YamiHead, Institutional Performance & QualityP-040t.alyami@chamber.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-05-21 | 2026-07-07 | +47 days | Tariq S. Al-YamiTariq S. Al-YamiHead, Institutional Performance & QualityP-040t.alyami@chamber.sa | Achieved | 1 | Approved |
| Final handoverMS-G5 | Payment | 2026-08-31 | 2026-10-26 | +56 days | Tariq S. Al-YamiTariq S. Al-YamiHead, Institutional Performance & QualityP-040t.alyami@chamber.sa | Achieved | 1 | Approved |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
100%Awaiting acceptance
0%Not handed in
0%Deliverable flow
Display options
| Project plan & baseline030-D1 | 5% | CRT-030-01 | Approved | Tariq S. Al-YamiTariq S. Al-YamiHead, Institutional Performance & QualityP-040t.alyami@chamber.sa | Dr. Amal F. Al-Sudairi | 2025-05-30 | V1 | 3 of 3 |
| Monitoring & reporting030-D2 | 5% | CRT-030-02 | Approved | Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & the PMOP-015a.alsudairi@chamber.sa | Dr. Amal F. Al-Sudairi | 2025-07-19 | V1 | 3 of 3 |
| Current-state assessment030-D3 | 10% | CRT-030-03 | Approved | Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & the PMOP-015a.alsudairi@chamber.sa | Dr. Amal F. Al-Sudairi | 2025-09-08 | V1 | 3 of 3 |
| Benchmarking030-D4 | 10% | CRT-030-04 | Approved | Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceP-009m.alsubaie@chamber.sa | Dr. Amal F. Al-Sudairi | 2025-10-29 | V1 | 3 of 3 |
| Target model030-D5 | 15% | CRT-030-05 | Approved | Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceP-009m.alsubaie@chamber.sa | Dr. Amal F. Al-Sudairi | 2025-12-19 | V1 | 3 of 3 |
| Roadmap030-D6 | 15% | CRT-030-06 | Approved | Tariq S. Al-YamiTariq S. Al-YamiHead, Institutional Performance & QualityP-040t.alyami@chamber.sa | Dr. Amal F. Al-Sudairi | 2026-02-08 | V1 | 3 of 3 |
| Wave 1030-D7 | 15% | CRT-030-07 | Approved | Tariq S. Al-YamiTariq S. Al-YamiHead, Institutional Performance & QualityP-040t.alyami@chamber.sa | Dr. Amal F. Al-Sudairi | 2026-03-31 | V1 | 3 of 3 |
| Wave 2030-D8 | 15% | CRT-030-08 | Approved | Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & the PMOP-015a.alsudairi@chamber.sa | Dr. Amal F. Al-Sudairi | 2026-05-21 | V1 | 3 of 3 |
| Knowledge transfer030-D9 | 5% | CRT-030-09 | Approved | Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & the PMOP-015a.alsudairi@chamber.sa | Dr. Amal F. Al-Sudairi | 2026-07-11 | V1 | 3 of 3 |
| Final report030-D10 | 5% | CRT-030-10 | Approved | Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceP-009m.alsubaie@chamber.sa | Dr. Amal F. Al-Sudairi | 2026-08-31 | V1 | 3 of 3 |
| Total · 10 | 100% |