Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-030On track5ClosureWaterfallIn progress

Enterprise Risk & Business Continuity Framework

Add to watchlist

A risk framework, register and appetite approved by the board, in line with ISO requirements.

Project managerTariq S. Al-YamiProject sponsorDr. Mohammed I. Al-Subaie

Budget (BAC)

SAR 180K

Actual cost

SAR 173K

⁦96%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 173K

SPI · CPI

1.00Schedule performance index · 1.001.04Cost performance index · 1.04

Forecast finish

⁦2026-08-31⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate3 June 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate19 July 2026Closure · Current stageClosure · Current stage

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
RC-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-01-19⁩
Hijri
30 Rajab 1447 AH
ApprovedCRT-030-05Target model

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-030
Project
Enterprise Risk & Business Continuity Framework
Portfolio
Institutional Excellence & Capability Portfolio
Sector
Strategy & Institutional Excellence
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Tariq S. Al-Yami

1The deliverableAuto-filled

DeliverableAuto-filled
Target model
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Dr. Mohammed I. Al-Subaie
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦15%⁩
DueAuto-filled
⁦2025-12-19⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-030_3.1_v1.pdfV1Dr. Mohammed I. Al-Subaie⁦2025-10-21⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Dr. Amal F. Al-Sudairi
Accepted byAuto-filled
Dr. Mohammed I. Al-Subaie
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Build complete
ContractAuto-filled
—
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Dr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceSubmitted—⁦2025-10-21⁩ 11:32
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-10-22⁩ 11:20
3Inspection & technical acceptance — ownerTechnical acceptanceDr. Mohammed I. Al-SubaieProject ownerOn behalf of Dr. Amal F. Al-SudairiApprovedInspected and accepted against the approved acceptance criteria.⁦2025-10-23⁩ 12:27
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-10-27⁩ 10:31
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-10-28⁩ 11:08

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2025-10-22⁩

Inspection & technical acceptance — owner

Dr. Mohammed I. Al-Subaie

Approved⁦2025-10-23⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2025-10-27⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2025-10-28⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Dr. Mohammed I. Al-Subaie on ⁦2025-10-21⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-10-22⁩ at ⁦11:20⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Dr. Amal F. Al-Sudairi · Project owner

    Approved · ⁦2025-10-23⁩ at ⁦12:27⁩ · On behalf of Dr. Amal F. Al-Sudairi (Dr. Mohammed I. Al-Subaie)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-10-27⁩ at ⁦10:31⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-10-28⁩ at ⁦11:08⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-10-21⁩

    PRJ-2026-030_3.1_v1.pdf

    Dr. Mohammed I. Al-Subaie

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close