1.00Schedule performance index · 1.001.04Cost performance index · 1.04
Forecast finish
2026-08-31
On baseline
Closure·Stage 5 of 5
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
Gate into «Execution»DecisionGoDate3 June 2025Execution · CompleteExecution · Complete
Gate into «Closure»DecisionGoDate19 July 2026Closure · Current stageClosure · Current stage
Baselines
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Original baseline
v1.0Approved & lockedVersion A
Finish
2026-08-31
Budget
SAR 180K
15 activities
Approved with the project plan at the planning gate.
Approved 2025-03-09 · by Dr. Mohammed I. Al-Subaie
Working
Working baseline
v2.0-draftWorking draftVersion B
Finish
2026-10-26
+56 days
Budget
SAR 180K
15 activities
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Each line starts at the milestone’s date in A and ends at its date in B
2025-072026-012026-07
Project plan approved+15
Designs approved+26
Build complete+36
Testing & acceptance complete+47
Final handover+56
Version AVersion B
Cost by WBS element
Difference in SAR millions from A to B
1Management & governance−0.00
2Diagnosis−0.00
3Design+0.00
4Implementation−0.00
5Handover & knowledge transfer−0.00
Version history
Every saved version with its reason and reference
Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.2026-10-28by Tariq S. Al-Yami
Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.2025-03-09by Dr. Mohammed I. Al-Subaie