Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-030On track5ClosureWaterfallIn progress

Enterprise Risk & Business Continuity Framework

Add to watchlist

A risk framework, register and appetite approved by the board, in line with ISO requirements.

Project managerTariq S. Al-YamiProject sponsorDr. Mohammed I. Al-Subaie

Budget (BAC)

SAR 180K

Actual cost

SAR 173K

⁦96%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 173K

SPI · CPI

1.00Schedule performance index · 1.001.04Cost performance index · 1.04

Forecast finish

⁦2026-08-31⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate3 June 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate19 July 2026Closure · Current stageClosure · Current stage

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+56⁩ days vs approved

Baseline (original = approved) · By earned schedule⁦2026-08-31⁩
Current forecast⁦2026-10-26⁩
Critical activities
0
of ⁦0⁩ open activities
Late activities
0
past their baseline finish
Schedule performance
1.00
earned ÷ planned value
Breached constraints
0
binding dates that will be missed
Expand allCollapse all
Activity
Enterprise Risk & Business Continuity FrameworkPlanned: ⁦2025-03-09⁩ → ⁦2026-08-31⁩Actual: ⁦2025-03-09⁩ → ⁦2026-10-26⁩
Management & governancePlanned: ⁦2025-03-09⁩ → ⁦2025-07-19⁩Actual: ⁦2025-03-09⁩ → ⁦2025-08-03⁩
Project plan & baselinePlanned: ⁦2025-03-09⁩ → ⁦2025-05-30⁩Actual: ⁦2025-03-09⁩ → ⁦2025-06-07⁩
Monitoring & reportingPlanned: ⁦2025-04-29⁩ → ⁦2025-07-19⁩Actual: ⁦2025-05-04⁩ → ⁦2025-08-03⁩
Project plan approvedPlanned: ⁦2025-07-19⁩ → ⁦2025-07-19⁩Actual: ⁦2025-08-03⁩ → ⁦2025-08-03⁩Project plan approved
DiagnosisPlanned: ⁦2025-06-19⁩ → ⁦2025-10-29⁩Actual: ⁦2025-06-30⁩ → ⁦2025-11-24⁩
Current-state assessmentPlanned: ⁦2025-06-19⁩ → ⁦2025-09-08⁩Actual: ⁦2025-06-30⁩ → ⁦2025-09-28⁩
BenchmarkingPlanned: ⁦2025-08-09⁩ → ⁦2025-10-29⁩Actual: ⁦2025-08-25⁩ → ⁦2025-11-24⁩
Designs approvedPlanned: ⁦2025-10-29⁩ → ⁦2025-10-29⁩Actual: ⁦2025-11-24⁩ → ⁦2025-11-24⁩Designs approved
DesignPlanned: ⁦2025-09-29⁩ → ⁦2026-02-08⁩Actual: ⁦2025-10-21⁩ → ⁦2026-03-16⁩
Target modelPlanned: ⁦2025-09-29⁩ → ⁦2025-12-19⁩Actual: ⁦2025-10-21⁩ → ⁦2026-01-19⁩
RoadmapPlanned: ⁦2025-11-19⁩ → ⁦2026-02-08⁩Actual: ⁦2025-12-16⁩ → ⁦2026-03-16⁩
Build completePlanned: ⁦2026-02-08⁩ → ⁦2026-02-08⁩Actual: ⁦2026-03-16⁩ → ⁦2026-03-16⁩Build complete
ImplementationPlanned: ⁦2026-01-09⁩ → ⁦2026-05-21⁩Actual: ⁦2026-02-10⁩ → ⁦2026-07-07⁩
Wave 1Planned: ⁦2026-01-09⁩ → ⁦2026-03-31⁩Actual: ⁦2026-02-10⁩ → ⁦2026-05-12⁩
Wave 2Planned: ⁦2026-03-01⁩ → ⁦2026-05-21⁩Actual: ⁦2026-04-08⁩ → ⁦2026-07-07⁩
Testing & acceptance completePlanned: ⁦2026-05-21⁩ → ⁦2026-05-21⁩Actual: ⁦2026-07-07⁩ → ⁦2026-07-07⁩Testing & acceptance complete
Handover & knowledge transferPlanned: ⁦2026-04-21⁩ → ⁦2026-08-31⁩Actual: ⁦2026-06-03⁩ → ⁦2026-10-26⁩
Knowledge transferPlanned: ⁦2026-04-21⁩ → ⁦2026-07-11⁩Actual: ⁦2026-06-03⁩ → ⁦2026-09-02⁩
Final reportPlanned: ⁦2026-06-10⁩ → ⁦2026-08-31⁩Actual: ⁦2026-07-30⁩ → ⁦2026-10-26⁩
Final handoverPlanned: ⁦2026-08-31⁩ → ⁦2026-08-31⁩Actual: ⁦2026-10-26⁩ → ⁦2026-10-26⁩Final handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦21⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦0⁩ open activities, data date ⁦2026-10-28⁩

Slippage pattern⁦84%⁩ confidence

Milestones slip 36 days on average — and it is getting worse

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

15
26
36
47
56
G1G2G3G4G5

The critical chain

In date order, to final acceptance

No open critical activities

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close