AI insight
No early warning on this project
Only a 8% chance of a further slip on current trends.
Turning the four pillars and their twelve objectives into department operational plans, OKRs and measurement cycles.
Budget (BAC)
Actual cost
70% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure27 November 2026
A weighted index, not just percent complete; each dimension leads to the tab that explains it.
Health index
89
Solid
Index over the last six reports
May to October 2026
No material change in the health dimensions over the period.
AI insight
Only a 8% chance of a further slip on current trends.
Generated from the live project data
The project is close to plan: 70% done against 68% planned.
SPI 1.03, CPI 1.00.
How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.
The main objective and initiative, the secondary links, and the project’s contribution to its initiative.
Main initiative
SI-4.2.2Performance measurement & governance
The project’s share of the initiative’s project budget (3 projects)
Secondary links
No secondary links
Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.
Counted
70%Awaiting acceptance 11%
Not handed in 19%
6 deliverables accepted
1 deliverable under inspection or acceptance
3 of 5 milestones complete
Earned-value curve
Planned, earned and actual to the data date, cumulative, with the forecast cost tail
Commitments are 94% of budget
0 approvals and 0 open actions on this project
0 open risks, exposure SAR 0
Impact
0 escalated
6 of 10 approved
3 members