Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-028On track4ExecutionWaterfallIn progress

Operational Plans & Scorecards for the 2025–2030 Strategy

Add to watchlist

Turning the four pillars and their twelve objectives into department operational plans, OKRs and measurement cycles.

Budget (BAC)

SAR 160K

Actual cost

SAR 112K

⁦70%⁩ of budget

Progress

⁦70%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 160K

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦0⁩ days vs approved

Baseline (original = approved) · Current forecast⁦2026-12-15⁩
By earned schedule⁦2027-01-23⁩
Critical activities
1
of ⁦6⁩ open activities
Late activities
3
past their baseline finish
Schedule performance
0.83
earned ÷ planned value
Next milestone
in 25 days
Testing & acceptance complete
Expand allCollapse all
Activity
Operational Plans & Scorecards for the 2025–2030 StrategyPlanned: ⁦2026-05-03⁩ → ⁦2026-12-15⁩Forecast: ⁦2026-05-03⁩ → ⁦2026-12-15⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2026-05-03⁩ → ⁦2026-06-27⁩Actual: ⁦2026-05-03⁩ → ⁦2026-07-12⁩
Project plan & baselinePlanned: ⁦2026-05-03⁩ → ⁦2026-06-06⁩Actual: ⁦2026-05-03⁩ → ⁦2026-06-15⁩
Monitoring & reportingPlanned: ⁦2026-05-24⁩ → ⁦2026-06-27⁩Actual: ⁦2026-05-30⁩ → ⁦2026-07-12⁩
Project plan approvedPlanned: ⁦2026-06-27⁩ → ⁦2026-06-27⁩Actual: ⁦2026-07-12⁩ → ⁦2026-07-12⁩Project plan approved
DiagnosisPlanned: ⁦2026-06-15⁩ → ⁦2026-08-09⁩Actual: ⁦2026-06-26⁩ → ⁦2026-09-04⁩
Current-state assessmentPlanned: ⁦2026-06-15⁩ → ⁦2026-07-19⁩Actual: ⁦2026-06-26⁩ → ⁦2026-08-08⁩
BenchmarkingPlanned: ⁦2026-07-06⁩ → ⁦2026-08-09⁩Actual: ⁦2026-07-23⁩ → ⁦2026-09-04⁩
Designs approvedPlanned: ⁦2026-08-09⁩ → ⁦2026-08-09⁩Actual: ⁦2026-09-04⁩ → ⁦2026-09-04⁩Designs approved
DesignPlanned: ⁦2026-07-27⁩ → ⁦2026-09-21⁩Actual: ⁦2026-08-19⁩ → ⁦2026-10-26⁩
Target modelPlanned: ⁦2026-07-27⁩ → ⁦2026-08-30⁩Actual: ⁦2026-08-19⁩ → ⁦2026-10-01⁩
RoadmapPlanned: ⁦2026-08-18⁩ → ⁦2026-09-21⁩Actual: ⁦2026-09-15⁩ → ⁦2026-10-26⁩
Build completePlanned: ⁦2026-09-21⁩ → ⁦2026-09-21⁩Actual: ⁦2026-10-26⁩ → ⁦2026-10-26⁩Build complete
ImplementationPlanned: ⁦2026-09-08⁩ → ⁦2026-11-02⁩Forecast: ⁦2026-09-08⁩ → ⁦2026-11-22⁩Float: ⁦1⁩d
Wave 1Planned: ⁦2026-09-08⁩ → ⁦2026-10-12⁩Forecast: ⁦2026-09-08⁩ → ⁦2026-11-11⁩Float: ⁦1⁩dDrag to change its duration+30
Wave 2Planned: ⁦2026-09-29⁩ → ⁦2026-11-02⁩Forecast: ⁦2026-11-04⁩ → ⁦2026-11-22⁩Float: ⁦1⁩dDrag to change its dates+20
Testing & acceptance completePlanned: ⁦2026-11-02⁩ → ⁦2026-11-02⁩Forecast: ⁦2026-11-22⁩ → ⁦2026-11-22⁩Float: ⁦23⁩dDrag to change its datesTesting & acceptance complete
Handover & knowledge transferPlanned: ⁦2026-10-21⁩ → ⁦2026-12-15⁩Forecast: ⁦2026-11-15⁩ → ⁦2026-12-15⁩Float: ⁦0⁩d
Knowledge transferPlanned: ⁦2026-10-21⁩ → ⁦2026-11-24⁩Forecast: ⁦2026-11-15⁩ → ⁦2026-12-03⁩Float: ⁦1⁩dDrag to change its dates+9
Final reportPlanned: ⁦2026-11-11⁩ → ⁦2026-12-15⁩Forecast: ⁦2026-11-26⁩ → ⁦2026-12-14⁩Float: ⁦1⁩dDrag to change its dates
Final handoverPlanned: ⁦2026-12-15⁩ → ⁦2026-12-15⁩Forecast: ⁦2026-12-15⁩ → ⁦2026-12-15⁩Float: ⁦0⁩dDrag to change its datesFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦21⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦6⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦0⁩ activities with no float

Every day lost on this chain is a day lost at launch. ⁦4⁩ more activities have three weeks of float or less.
Slippage pattern⁦84%⁩ confidence

Milestones slip 19 days on average

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

15
26
35
20
0
G1G2G3G4G5

The critical chain

In date order, to final acceptance

Near-critical

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close