PRJ-2026-028On track4ExecutionWaterfallIn progress

Operational Plans & Scorecards for the 2025–2030 Strategy

Add to watchlist

Turning the four pillars and their twelve objectives into department operational plans, OKRs and measurement cycles.

Budget (BAC)

SAR 160K

Actual cost

SAR 112K

⁦70%⁩ of budget

Progress

⁦70%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 160K

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2026-12-15⁩
    Budget
    SAR 160K
    ⁦15⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2026-05-03⁩ · by Dr. Mohammed I. Al-Subaie

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2026-12-15⁩
    Budget
    SAR 160K
    ⁦15⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Abeer H. Al-Shamrani

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2026-12-15⁩⁦2026-12-15⁩

⁦0⁩ days

Budget

SAR 160KSAR 160K

⁦0.00⁩ SAR M

Milestones moved

4 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2026-072027-01
  • Project plan approved⁦+15⁩
  • Designs approved⁦+26⁩
  • Build complete⁦+35⁩
  • Testing & acceptance complete⁦+20⁩
  • Final handover

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Management & governance⁦+0.00⁩
  • 2Diagnosis⁦+0.00⁩
  • 3Design⁦+0.00⁩
  • 4Implementation⁦−0.00⁩
  • 5Handover & knowledge transfer⁦+0.00⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Abeer H. Al-Shamrani
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2026-05-03⁩by Dr. Mohammed I. Al-Subaie