PRJ-2026-028On track4ExecutionWaterfallIn progress

Operational Plans & Scorecards for the 2025–2030 Strategy

Add to watchlist

Turning the four pillars and their twelve objectives into department operational plans, OKRs and measurement cycles.

Budget (BAC)

SAR 160K

Actual cost

SAR 112K

⁦70%⁩ of budget

Progress

⁦70%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 160K

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 160K split into spent, committed and left, with the estimate at completion

EAC SAR 160K
Revised request SAR 160K
  • Actual spendSAR 112K
  • Committed, not spentSAR 38K
  • Allotted, uncommittedSAR 5,200
  • Contingency availableSAR 4,800

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 165K
Original budgetwhen the first baseline was approved
SAR 160K
Approved budgetafter approved change requests
SAR 160K
Current budgetavailable to spend now
SAR 160K
Revised budgetif the pending changes are approved
SAR 160K

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 150K
Contracts1 active contract
SAR 145K
Purchase orders⁦1⁩ order
SAR 5,000
Remaining budgetapproved less actual
SAR 48K

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 112K
Accrualswork done, not yet invoiced
SAR 4,000
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 160K
ContingencySAR 3,200 drawn of SAR 8,000
SAR 4,800

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 165K
ApprovedSAR 160K
Estimate at completionSAR 160K
Approved is SAR 5,000 (⁦3.0%⁩) below the estimate
The estimate at completion is SAR 5,000 (⁦3.0%⁩) below the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2026-02-17⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-21028
  • WBS elements⁦5⁩ elements · P-2026-028.01 …
  • Purchase orders⁦1⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦3⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 3,200 drawn of SAR 8,000

  • Covering realised delivery risks⁦2026-08-29⁩SAR 3,200

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance0.020.020.020.02⁦−0.00⁩
2Diagnosis0.030.030.030.03⁦−0.00⁩
3Design0.050.050.050.05⁦−0.00⁩
4Implementation0.050.040.020.05⁦+0.00⁩
5Handover & knowledge transfer0.020.010.000.02⁦−0.00⁩
Unallocated contingency0.000.000.000.00⁦+0.00⁩
Total0.160.150.110.16⁦+0.00⁩

Budget split

WBS

SAR 160K

Budget

  • Management & governanceSAR 15.5K⁦10%⁩
  • DiagnosisSAR 31K⁦19%⁩
  • DesignSAR 46.6K⁦29%⁩
  • ImplementationSAR 46.6K⁦29%⁩
  • Handover & knowledge transferSAR 15.5K⁦10%⁩
  • Unallocated contingencySAR 4,800⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2027-01-23⁩+39

SPI(t) ⁦0.85⁩ against the approved finish ⁦2026-12-15⁩

Planned valuePV
SAR 135K
The value of the work that should be done by today.
PV
Earned valueEV
SAR 112K
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 112K
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 160K
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.00⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−0.02⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.00
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.83
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 160K
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 48K
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.00⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 160K
  • If the rest goes to planSAR 160K
  • At cost and schedule performanceSAR 169.9K
  • The PM’s bottom-up estimateSAR 160K
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 160K

Variance at completion: ⁦+0.00⁩ SAR M