Operational Plans & Scorecards for the 2025–2030 Strategy
Add to watchlistTurning the four pillars and their twelve objectives into department operational plans, OKRs and measurement cycles.
Budget (BAC)
Actual cost
70% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure27 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started
Project documents by stage
What each stage requires under the RFP, what has been filed and what is missing, and the evidence tied to deliverables.
Mandatory complete
0
of 7
- 0 of 7 mandatory documents due
- 7 mandatory documents missing
- 1 document in the repository
Documents in the project folder
Archived automatically when the project closes, and kept read-only under the retention policy.
Stages and required documents
For each of the five stages, what its gates and forms require: present, missing, or not yet due.
- 1Pre-start
Project proposal & feasibility studyMandatory· Missing
Approval gate G1
Priority & weight assessmentOptional· Missing
Annual work plan
- 2Initiation
Approved project charterMandatory· Missing
Initiation gate G2
Kick-off meeting minutesMandatory· Missing
Initiation gate G2
- 3Planning
Project management plan, schedule & baselineMandatory· Missing
Planning gate G3
Contract or purchase orderMandatory· Missing
Finance & procurement — when there is a contract
Technical studies & drawingsOptional· Missing
Project management plan
Other documents in the stage
Draft operational plans for the 2025–2030 strategy
- 4ExecutionCurrent stage
Periodic update cards & status reportsMandatory· Missing
Periodic update card form
Deliverable completion certificatesMandatory· Missing
Deliverable completion certificate form
Corrective plan when off trackOptional· Missing
Corrective plan form
- 5Closure
Project closure & handover formMandatory· Not yet due
Closure gate G4
Lessons learnedMandatory· Not yet due
Closure gate G4
Acceptance test resultsOptional· Not yet due
Deliverable acceptance
Documents linked to stages and tasks
Each document is tied to its stage of the project lifecycle and to the plan activities it serves — pick an activity to open it on the schedule
- DOC-0219V1Draft operational plans for the 2025–2030 strategy3PlanningNot linked to a task yet
Evidence tied to deliverables
Each deliverable with its repository document and the files that prove it.
- 028-D1Project plan & baselinePRJ-2026-028_1.1_v1.pdfApprovedDeliverable
- 028-D2Monitoring & reportingPRJ-2026-028_1.2_v1.pdfApprovedDeliverable
- 028-D3Current-state assessmentPRJ-2026-028_2.1_v1.pdfApprovedDeliverable
- 028-D4BenchmarkingPRJ-2026-028_2.2_v1.pdfApprovedDeliverable
- 028-D5Target modelPRJ-2026-028_3.1_v1.pdfApprovedDeliverable
- 028-D6RoadmapPRJ-2026-028_3.2_v1.pdfApprovedDeliverable
- 028-D7Wave 1PRJ-2026-028_4.1_v1.pdfIn reviewDeliverable
- 028-D8Wave 2No evidence filed yetDraftDeliverable
- 028-D9Knowledge transferNo evidence filed yetDraftDeliverable
- 028-D10Final reportNo evidence filed yetDraftDeliverable