PRJ-2026-028On track4ExecutionWaterfallIn progress

Operational Plans & Scorecards for the 2025–2030 Strategy

Add to watchlist

Turning the four pillars and their twelve objectives into department operational plans, OKRs and measurement cycles.

Budget (BAC)

SAR 160K

Actual cost

SAR 112K

⁦70%⁩ of budget

Progress

⁦70%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 160K

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

3Achieved
2On track
0At risk
0Late
Average delay19 days
Jul 26Oct 26
Contractual
Build completePlanned: ⁦2026-09-21⁩Forecast / actual: ⁦2026-10-26⁩Delay: 35 daysG3 +35
Executive
Project plan approvedPlanned: ⁦2026-06-27⁩Forecast / actual: ⁦2026-07-12⁩Delay: 15 daysG1 +15
Payment
Final handoverPlanned: ⁦2026-12-15⁩Forecast / actual: ⁦2026-12-15⁩G5
Regulatory
Testing & acceptance completePlanned: ⁦2026-11-02⁩Forecast / actual: ⁦2026-11-22⁩Delay: 20 daysG4 +20
Project
Designs approvedPlanned: ⁦2026-08-09⁩Forecast / actual: ⁦2026-09-04⁩Delay: 26 daysG2 +26

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2026-06-27⁩⁦2026-07-12⁩⁦+15⁩ daysAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@chamber.saAchieved1Approved
Designs approvedMS-G2Project⁦2026-08-09⁩⁦2026-09-04⁩⁦+26⁩ daysAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@chamber.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-09-21⁩⁦2026-10-26⁩⁦+35⁩ daysAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@chamber.saAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2026-11-02⁩⁦2026-11-22⁩⁦+20⁩ daysAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@chamber.saOn track0Not requested
Final handoverMS-G5Payment⁦2026-12-15⁩⁦2026-12-15⁩On timeAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@chamber.saOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦70%⁩

Awaiting acceptance

⁦11%⁩

Not handed in

⁦19%⁩

Deliverable flow

Pick a stage to filter the register
⁦10⁩ results
Export CSV
Project plan & baseline028-D1⁦6%⁩CRT-028-01ApprovedAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@chamber.saDr. Amal F. Al-Sudairi⁦2026-06-06⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting028-D2⁦6%⁩CRT-028-02ApprovedDr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & the PMOP-015a.alsudairi@chamber.saDr. Amal F. Al-Sudairi⁦2026-06-27⁩V1⁦3⁩ of ⁦3⁩
Current-state assessment028-D3⁦12%⁩CRT-028-03ApprovedDr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & the PMOP-015a.alsudairi@chamber.saDr. Amal F. Al-Sudairi⁦2026-07-19⁩V1⁦3⁩ of ⁦3⁩
Benchmarking028-D4⁦12%⁩CRT-028-04ApprovedDr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceP-009m.alsubaie@chamber.saDr. Amal F. Al-Sudairi⁦2026-08-09⁩V1⁦3⁩ of ⁦3⁩
Target model028-D5⁦17%⁩CRT-028-05ApprovedDr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceP-009m.alsubaie@chamber.saDr. Amal F. Al-Sudairi⁦2026-08-30⁩V1⁦3⁩ of ⁦3⁩
Roadmap028-D6⁦17%⁩CRT-028-06ApprovedAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@chamber.saDr. Amal F. Al-Sudairi⁦2026-09-21⁩V1⁦3⁩ of ⁦3⁩
Wave 1028-D7⁦11%⁩—Under reviewAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@chamber.saDr. Amal F. Al-Sudairi⁦2026-10-12⁩V1⁦1⁩ of ⁦3⁩
Wave 2028-D8⁦11%⁩—DraftDr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & the PMOP-015a.alsudairi@chamber.saDr. Amal F. Al-Sudairi⁦2026-11-02⁩V0⁦0⁩ of ⁦3⁩
Knowledge transfer028-D9⁦4%⁩—DraftDr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & the PMOP-015a.alsudairi@chamber.saDr. Amal F. Al-Sudairi⁦2026-11-24⁩V0⁦0⁩ of ⁦3⁩
Final report028-D10⁦4%⁩—DraftDr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceP-009m.alsubaie@chamber.saDr. Amal F. Al-Sudairi⁦2026-12-15⁩V0⁦0⁩ of ⁦3⁩
Total · 10⁦100%⁩
⁦1⁩–⁦10⁩ of ⁦10⁩