Certificate ⁦7⁩ — March 2026

New Premium Members Centre & VIP lounges — fit-out

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
7
Date
⁦2026-04-08⁩
Hijri
20 Shawwal 1447 AH
Reference
PAY-2025-023-07

Interim payment certificate no. (⁦7⁩)

For the work of March 2026

Contract number
RC/2025/023
Supplier-portal reference
2504720693
Contract
New Premium Members Centre & VIP lounges — fit-out
Contractor
Coastline Contracting & Development Co.
Contractor VAT number
340303951060003
Project
New Premium Members Centre & VIP Lounges
Contract period
⁦2025-04-06⁩ — ⁦2027-02-28⁩
Original contract value
5,900,000
Current contract value
5,900,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date2,484,500
2Less: previous certificates(2,036,000)
3Value of work in this certificate448,500
4Less: retention (⁦10%⁩)(44,850)
5Less: advance payment recovery (⁦10%⁩)(44,850)
6Less: delay and breach penalties0
7Total deductions(89,700)
8Net before VAT358,800
9Add: value added tax (15%)53,820
10Net amount payable to the contractor412,620

Amount in words: Four hundred twelve thousand six hundred twenty Saudi riyals only

Retention held up to this certificate: SAR 248.5K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation413,000339,10062,150401,250⁦97%⁩
Earthworks & foundations1,062,000524,900101,200626,100⁦59%⁩
Concrete & structural works1,829,000693,100154,100847,200⁦46%⁩
Mechanical, electrical & plumbing1,416,000330,25087,150417,400⁦29%⁩
Finishes & external works885,000129,85037,850167,700⁦19%⁩
Testing & commissioning295,00018,8006,05024,850⁦8%⁩
Total5,900,0002,036,000448,5002,484,500⁦42%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Talal H. Al-Ghamdi

Al-Ghamdi⁦2026-04-08⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-04-10⁩

Project manager

Eng. Fahad T. Al-Sulami

Al-Sulami⁦2026-04-13⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-04-16⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-04-19⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-04-08⁩

    Eng. Talal H. Al-Ghamdi

  2. Engineer verifies quantities⁦2026-04-10⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-04-13⁩

    Eng. Fahad T. Al-Sulami · Senior Project Manager — Branches & Service Centres

    Took 3 days

  4. Payment order prepared⁦2026-04-16⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-04-19⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2026-04-22⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Fahad T. Al-Sulami → Dr. Abdullah S. Al-Qahtani

Certificate history

19 April 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-04-19 13:00

16 April 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-04-16 13:00

13 April 2026

  1. Approval: Eng. Fahad T. Al-Sulami signed “Project manager certifies”

    2026-04-13 13:00

10 April 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-04-10 13:00

8 April 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-04-08 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close