Certificate ⁦8⁩ — May 2026

New Premium Members Centre & VIP lounges — fit-out

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
8
Date
⁦2026-06-01⁩
Hijri
15 Dhuʻl-Hijjah 1447 AH
Reference
PAY-2025-023-08

Interim payment certificate no. (⁦8⁩)

For the work of May 2026

Contract number
RC/2025/023
Supplier-portal reference
2504720693
Contract
New Premium Members Centre & VIP lounges — fit-out
Contractor
Coastline Contracting & Development Co.
Contractor VAT number
340303951060003
Project
New Premium Members Centre & VIP Lounges
Contract period
⁦2025-04-06⁩ — ⁦2027-02-28⁩
Original contract value
5,900,000
Current contract value
5,900,000
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SAR)

1Total value of work completed to date2,818,000
2Less: previous certificates(2,484,500)
3Value of work in this certificate333,500
4Less: retention (⁦10%⁩)(33,350)
5Less: advance payment recovery (⁦10%⁩)(33,350)
6Less: delay and breach penalties0
7Total deductions(66,700)
8Net before VAT266,800
9Add: value added tax (15%)40,020
10Net amount payable to the contractor306,820

Amount in words: Three hundred six thousand eight hundred twenty Saudi riyals only

Retention held up to this certificate: SAR 281.8K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation413,000372,50040,500413,000⁦100%⁩
Earthworks & foundations1,062,000674,45077,800752,250⁦71%⁩
Concrete & structural works1,829,000846,300114,650960,950⁦53%⁩
Mechanical, electrical & plumbing1,416,000406,85066,550473,400⁦33%⁩
Finishes & external works885,000160,95029,250190,200⁦21%⁩
Testing & commissioning295,00023,4504,75028,200⁦10%⁩
Total5,900,0002,484,500333,5002,818,000⁦48%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Talal H. Al-Ghamdi

Al-Ghamdi⁦2026-06-01⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-06-03⁩

Project manager

Eng. Fahad T. Al-Sulami

Al-Sulami⁦2026-06-06⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-06-09⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-06-12⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-06-01⁩

    Eng. Talal H. Al-Ghamdi

  2. Engineer verifies quantities⁦2026-06-03⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-06-06⁩

    Eng. Fahad T. Al-Sulami · Senior Project Manager — Branches & Service Centres

    Took 3 days

  4. Payment order prepared⁦2026-06-09⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-06-12⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedLate · ⁦2026-09-29⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Fahad T. Al-Sulami → Dr. Abdullah S. Al-Qahtani

Certificate history

12 June 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-06-12 13:00

9 June 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-06-09 13:00

6 June 2026

  1. Approval: Eng. Fahad T. Al-Sulami signed “Project manager certifies”

    2026-06-06 13:00

3 June 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-06-03 13:00

1 June 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-06-01 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close